1547 S DURANGO AVE 90035
Certificate Information: 1547 S DURANGO AVE 90035
- Application / Permit
- 19014-10000-06379
- Plan Check / Job No.
- B19LA24905
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SECOND FLOOR ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING. NEW ATTACHED GARAGE.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | KEVIN MORALES |
| Corrections Issued | 12/3/2019 | KEVIN MORALES |
| Building Plans Picked Up | 12/13/2019 | APPLICANT |
| Quality Review Completed | 12/14/2019 | YOUNG KIM |
| Green Plans Picked Up | 1/30/2020 | APPLICANT |
| Plan Check Approved | 2/18/2020 | KEVIN MORALES |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 3/15/2021 | EVAN COOPER |
| Permit Finaled | 4/9/2021 | KENNETH NAGLE |
| CofO Issued | 4/9/2021 | KENNETH NAGLE |
| Permit Finaled | 4/9/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/16/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | ERIK BEASLEY |
| Permit | Cleared | 1/21/2020 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 1/21/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/21/2020 | ERIK BEASLEY |
| Trees in Parkway | Cleared | 1/23/2020 | JOHN KIM |
| Green Code | Cleared | 1/30/2020 | VIVIAN LAO |
| GPI Written Notices | Cleared | 2/5/2020 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 2/5/2020 | KEVIN MORALES |
Contact Information
| Contractor | Harari Construction Inc; Lic. No.: 1017539-B | 9719 OAKMORE ROAD LOS ANGELES, CA 90035 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/6/2020 | Partial Inspection | EVAN COOPER |
| Sewer | 3/6/2020 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 5/4/2020 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/7/2020 | Approved | EVAN COOPER |
| METHANE-Barrier | 5/7/2020 | Approved | EVAN COOPER |
| METHANE-Subgrade | 5/7/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 5/14/2020 | Partial Approval | EVAN COOPER |
| Sewer | 5/14/2020 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2020 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 7/31/2020 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 7/31/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 7/31/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/31/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 8/24/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 8/24/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/28/2020 | Approved | EVAN COOPER |
| Green Building Rough | 8/28/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/28/2020 | Partial Approval | EVAN COOPER |
| Shower Pan | 8/28/2020 | Approved | EVAN COOPER |
| Insulation | 9/9/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/10/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 9/30/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 2/23/2021 | Approved | EVAN COOPER |
| Final | 2/23/2021 | Corrections Issued | EVAN COOPER |
| Gas Test | 2/23/2021 | Approved | EVAN COOPER |
| HVAC-Final | 2/23/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/23/2021 | Approved | EVAN COOPER |
| Service/Power Release | 3/1/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 3/2/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 3/3/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 3/3/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 3/3/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 3/3/2021 | Approved | EVAN COOPER |
| Final | 3/10/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 3/10/2021 | Approved | EVAN COOPER |
| Service/Power Release | 3/10/2021 | Approved | EVAN COOPER |
| Final | 3/15/2021 | OK to Issue CofO | EVAN COOPER |