1547 S DURANGO AVE 90035

Certificate Information: 1547 S DURANGO AVE 90035

Application / Permit
19014-10000-06379
Plan Check / Job No.
B19LA24905
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SECOND FLOOR ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING. NEW ATTACHED GARAGE.
Permit Issued
Issued on 2/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 KEVIN MORALES
Corrections Issued 12/3/2019 KEVIN MORALES
Building Plans Picked Up 12/13/2019 APPLICANT
Quality Review Completed 12/14/2019 YOUNG KIM
Green Plans Picked Up 1/30/2020 APPLICANT
Plan Check Approved 2/18/2020 KEVIN MORALES
Issued 2/24/2020 LADBS
CofO in Progress 3/15/2021 EVAN COOPER
Permit Finaled 4/9/2021 KENNETH NAGLE
CofO Issued 4/9/2021 KENNETH NAGLE
Permit Finaled 4/9/2021 KENNETH NAGLE

Permit Application Clearance Information

Low Impact Development Cleared 1/16/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 1/21/2020 ERIK BEASLEY
Permit Cleared 1/21/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 1/21/2020 ERIK BEASLEY
Sewer availability Cleared 1/21/2020 ERIK BEASLEY
Trees in Parkway Cleared 1/23/2020 JOHN KIM
Green Code Cleared 1/30/2020 VIVIAN LAO
GPI Written Notices Cleared 2/5/2020 KEVIN MORALES
Grading Pre-Inspection Cleared 2/5/2020 KEVIN MORALES

Contact Information

Contractor Harari Construction Inc; Lic. No.: 1017539-B 9719 OAKMORE ROAD      LOS ANGELES, CA 90035
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/6/2020 Partial Inspection EVAN COOPER
Sewer 3/6/2020 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/4/2020 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/7/2020 Approved EVAN COOPER
METHANE-Barrier 5/7/2020 Approved EVAN COOPER
METHANE-Subgrade 5/7/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Corrections Issued EVAN COOPER
PLUMBING-Rough 5/14/2020 Partial Approval EVAN COOPER
Sewer 5/14/2020 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/10/2020 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Not Ready for Inspection EVAN COOPER
Gas Test 7/31/2020 Partial Approval EVAN COOPER
HVAC-Rough 7/31/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 7/31/2020 Approved EVAN COOPER
PLUMBING-Rough 7/31/2020 Approved EVAN COOPER
ELECTRICAL-Rough 8/24/2020 Approved EVAN COOPER
HVAC-Rough 8/24/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 8/28/2020 Approved EVAN COOPER
Green Building Rough 8/28/2020 Approved EVAN COOPER
Interior/Exterior Lathing 8/28/2020 Partial Approval EVAN COOPER
Shower Pan 8/28/2020 Approved EVAN COOPER
Insulation 9/9/2020 Approved EVAN COOPER
Interior/Exterior Lathing 9/10/2020 Approved EVAN COOPER
Drywall Nailing 9/30/2020 Approved EVAN COOPER
ELECTRICAL-Final 2/12/2021 Not Ready for Inspection EVAN COOPER
Final 2/12/2021 Not Ready for Inspection EVAN COOPER
Gas Test 2/12/2021 Not Ready for Inspection EVAN COOPER
Green Building Final 2/12/2021 Not Ready for Inspection EVAN COOPER
HVAC-Final 2/12/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 2/12/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Approved EVAN COOPER
Service/Power Release 2/12/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 2/12/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 2/23/2021 Approved EVAN COOPER
Final 2/23/2021 Corrections Issued EVAN COOPER
Gas Test 2/23/2021 Approved EVAN COOPER
HVAC-Final 2/23/2021 Approved EVAN COOPER
PLUMBING-Final 2/23/2021 Approved EVAN COOPER
Service/Power Release 3/1/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 3/2/2021 Not Ready for Inspection EVAN COOPER
Final 3/3/2021 Not Ready for Inspection EVAN COOPER
Green Building Final 3/3/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 3/3/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 3/3/2021 Approved EVAN COOPER
Final 3/10/2021 Corrections Issued EVAN COOPER
Green Building Final 3/10/2021 Approved EVAN COOPER
Service/Power Release 3/10/2021 Approved EVAN COOPER
Final 3/15/2021 OK to Issue CofO EVAN COOPER