1613 W FAIR PARK AVE 90041

Certificate Information: 1613 W FAIR PARK AVE 90041

Application / Permit
19014-10000-06373
Plan Check / Job No.
B19LA24860
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-car garage attached to front of (E) SFD and (N) driveway **COMPLY WITH DEPARTMENT ORDER effective date 03/04/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.**
Permit Issued
Issued on 1/8/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/4/2019 HELEN NGUYEN
Corrections Issued 12/4/2019 HELEN NGUYEN
Building Plans Picked Up 12/12/2019 APPLICANT
Plan Check Approved 1/7/2020 SINA KHOSRAVI
Issued 1/8/2020 LADBS
CofO in Progress 9/8/2020 DAVID LEE
CofO Issued 11/10/2020 DANIEL SANCHEZ
Permit Finaled 11/10/2020 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/4/2019 ELENA LOPEZ
Permit Cleared 12/4/2019 ELENA LOPEZ
Low Impact Development Cleared 1/7/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/7/2020 THOMAS LANG

Contact Information

Contractor B & C Construction Inc; Lic. No.: 1017702-B 4523 EAST 56TH STREET      MAYWOOD, CA 90270
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2020 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 1/14/2020 Approved DAVID LEE
Excavation/Setback/Form/Re-Bar 1/15/2020 Approved DAVID LEE
Footing/Foundation/Slab 1/15/2020 Approved DAVID LEE
BUILDING-Rough-Frame 1/28/2020 Conditional Approval DAVID LEE
Floor/Roof Diaphrgm/Shear Wall 1/28/2020 Conditional Approval DAVID LEE
Green Building Rough 1/28/2020 Approved DAVID LEE
Interior/Exterior Lathing 2/3/2020 Approved DAVID LEE
BUILDING-Rough-Frame 2/10/2020 Approved DAVID LEE
ELECTRICAL-Rough 2/10/2020 Approved DAVID LEE
Insulation 2/14/2020 Approved JUAN ESCOTO DELGADO
Drywall Nailing 2/19/2020 Approved DAVID LEE
Special/Order Compliance 3/9/2020 Approved DAVID LEE
ELECTRICAL-Final 5/7/2020 Approved DAVID LEE
Final 6/24/2020 Not Ready for Inspection DAVID LEE
Green Building Final 6/24/2020 Approved DAVID LEE
SGSOV-Seismic Gas S/O Valve 6/24/2020 SGSOV Approved DAVID LEE
Smoke Detectors 6/24/2020 Approved DAVID LEE
Final 9/8/2020 OK to Issue CofO DAVID LEE