3204-3204 1/2 E 3RD ST 90063
Certificate Information: 3204-3204 1/2 E 3RD ST 90063
- Application / Permit
- 19014-10000-06370
- Plan Check / Job No.
- B19LA24837
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to (E) SFD and conversion of entire new addition to ADU per ordinance 186,481.
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | HELEN NGUYEN |
| Corrections Issued | 12/19/2019 | MIGUEL JIMENEZ |
| Quality Review Completed | 12/24/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 12/27/2019 | APPLICANT |
| Green Plans Picked Up | 9/24/2020 | APPLICANT |
| Applicant returned to address corrections | 1/11/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/9/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/18/2021 | HELEN NGUYEN |
| Plan Check Approved | 2/23/2021 | HELEN NGUYEN |
| Issued | 2/25/2021 | APPLICANT |
| CofO in Progress | 6/7/2022 | FREDDIE RIVERA |
| No Progress | 6/7/2022 | FREDDIE RIVERA |
| CofO in Progress | 9/3/2022 | FREDDIE RIVERA |
| CofO Issued | 10/12/2022 | DEROLD HAUFF |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/10/2020 | THOMAS LANG |
| Green Code | Cleared | 9/23/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 11/19/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/1/2020 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 1/12/2021 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 2/9/2021 | MIGUEL JIMENEZ |
Contact Information
| Contractor | B & C Construction Inc; Lic. No.: 1017702-B | 4523 EAST 56TH STREET MAYWOOD, CA 90270 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 4/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 4/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/27/2021 | Approved | ROBERT VORHIS |
| METHANE-Barrier | 4/27/2021 | Approved | ROBERT VORHIS |
| METHANE-Subgrade | 4/27/2021 | Approved | ROBERT VORHIS |
| Sewer | 5/11/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 5/18/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 9/24/2021 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 11/16/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 11/16/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Rough | 11/16/2021 | Approved | ROBERT VORHIS |
| METHANE-Rough | 11/16/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 11/16/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 11/22/2021 | Approved | ROBERT VORHIS |
| HVAC-Rough | 11/22/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 11/22/2021 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 11/22/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 11/22/2021 | Approved | ROBERT VORHIS |
| Insulation | 11/30/2021 | Corrections Issued | RUBEN SALAS |
| Insulation | 12/6/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/6/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 12/16/2021 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 12/22/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/25/2022 | Corrections Issued | CRAIG DAVIS |
| Final | 2/25/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 2/25/2022 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/25/2022 | Corrections Issued | CRAIG DAVIS |
| Service/Power Release | 3/4/2022 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | FREDDIE RIVERA |
| Final | 4/27/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 4/27/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/27/2022 | Approved | FREDDIE RIVERA |
| Final | 5/20/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 5/20/2022 | Corrections Issued | FREDDIE RIVERA |
| Final | 5/26/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 5/26/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 6/6/2022 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 6/6/2022 | Approved | FREDDIE RIVERA |