6625 S CIMARRON ST 90047

Certificate Information: 6625 S CIMARRON ST 90047

Application / Permit
19014-10000-06368
Plan Check / Job No.
B19LA24836
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO AN ACCESSORY DWELLING UNIT WITH 17' X 20'-9"ADDITION PER AB 494 & SB 229. ALL WORK PER TYPE V SHEET.
Permit Issued
Issued on 2/4/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 12/6/2019 FARSHAD ALIMOHAMADI
Corrections Issued 12/6/2019 FARSHAD ALIMOHAMADI
Building Plans Picked Up 12/6/2019 APPLICANT
Plan Check Approved 12/18/2019 FARSHAD ALIMOHAMADI
Issued 2/4/2020 LADBS
CofO in Progress 10/25/2021 FREDDIE RIVERA
Permit Finaled 11/19/2021 DEROLD HAUFF
Permit Finaled 11/19/2021 DEROLD HAUFF
CofO Issued 11/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/11/2019 JEANIE LAM
Construction near power lines Cleared 12/11/2019 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/11/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 12/11/2019 JEANIE LAM
Sewer availability Cleared 12/11/2019 JEANIE LAM
ZI Cleared 12/11/2019 ANNA VIDAL

Contact Information

Contractor Gomez Construction; Lic. No.: 1049981-B 1151 S ALMA AVE      LOS ANGELES, CA 90023

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 4/9/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Approved FREDDIE RIVERA
HVAC-Rough 5/18/2020 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 5/18/2020 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 5/22/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/22/2020 Approved FREDDIE RIVERA
Green Building Rough 5/22/2020 Not Ready for Inspection FREDDIE RIVERA
Insulation 5/22/2020 Not Ready for Inspection FREDDIE RIVERA
Interior/Exterior Lathing 5/28/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/10/2020 Approved FREDDIE RIVERA
Green Building Rough 6/10/2020 Approved FREDDIE RIVERA
HVAC-Rough 6/10/2020 Approved FREDDIE RIVERA
Insulation 6/15/2020 No Access for Inspection SABAS ALONSO
Insulation 6/17/2020 Partial Approval SABAS ALONSO
Drywall Nailing 7/2/2020 Approved SABAS ALONSO
Insulation 7/2/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 7/13/2020 Approved SABAS ALONSO
Sewer 8/28/2020 Approved FREDDIE RIVERA
ELECTRICAL-Final 3/23/2021 Not Ready for Inspection FREDDIE RIVERA
Final 3/23/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 3/23/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 3/23/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Final 3/23/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 3/23/2021 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 3/23/2021 Approved FREDDIE RIVERA
ELECTRICAL-Final 4/5/2021 Approved FREDDIE RIVERA
Final 4/5/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 4/5/2021 Approved FREDDIE RIVERA
HVAC-Final 4/5/2021 Approved FREDDIE RIVERA
Insulation 4/5/2021 Approved FREDDIE RIVERA
PLUMBING-Final 4/5/2021 Approved FREDDIE RIVERA
Final 4/29/2021 Corrections Issued FREDDIE RIVERA
HVAC-Final 4/29/2021 Approved FREDDIE RIVERA
Final 8/30/2021 Not Ready for Inspection FREDDIE RIVERA
Final 10/21/2021 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 10/21/2021 Approved FREDDIE RIVERA