1876-1876 1/2 W 38TH PL 90062
Certificate Information: 1876-1876 1/2 W 38TH PL 90062
- Application / Permit
- 19014-10000-06335
- Plan Check / Job No.
- B19LA24715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE/PERGOLA INTO ADU PER AB 494 & SB 229
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 12/3/2019 | SERGIO GUTIERREZ |
| Green Plans Picked Up | 12/4/2019 | APPLICANT |
| Quality Review Completed | 12/24/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 12/26/2019 | APPLICANT |
| Plan Check Approved | 2/12/2020 | SERGIO GUTIERREZ |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 1/7/2021 | ROBERT MCDOWELL |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
| CofO Issued | 1/23/2021 | DEROLD HAUFF |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 2/6/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/6/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/6/2020 | JEANIE LAM |
| Green Code | Cleared | 2/11/2020 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Building Constuction & Steel Services; Lic. No.: 824092-B | PO BOX 63304 LOS ANGELES, CA 90063 |
Inspector Information
| RAUL BARAJAS, (213) 202-3211 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/9/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| ELECTRICAL-Rough | 9/9/2020 | Approved | DONALD CRICHLOW |
| Green Building Rough | 9/9/2020 | Approved | DONALD CRICHLOW |
| HVAC-Rough | 9/9/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Interior/Exterior Lathing | 9/9/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| PLUMBING-Rough | 9/9/2020 | Approved | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 11/17/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 11/17/2020 | Approved | ROBERT MCDOWELL |
| Final | 11/17/2020 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 11/17/2020 | Approved | ROBERT MCDOWELL |
| Gas Test | 11/17/2020 | Approved | ROBERT MCDOWELL |
| Green Building Final | 11/17/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 11/17/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 11/17/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 11/17/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 11/17/2020 | Approved | ROBERT MCDOWELL |
| Final | 1/7/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 1/7/2021 | SGSOV Approved | ROBERT MCDOWELL |