22968 W CALVERT ST 91367
Certificate Information: 22968 W CALVERT ST 91367
- Application / Permit
- 19014-10000-06290
- Plan Check / Job No.
- B19LA24592
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION WITH BEDROOM, 2 1/2 BATHROOMS, REC ROOM, LAUNDRY ROOM. 1 OF 2
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- Valley
- Current Status
- Issued on 2/11/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 12/2/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/24/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Green Plans Picked Up | 1/6/2020 | APPLICANT |
| Applicant returned to address corrections | 1/17/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/31/2020 | SERGIO GUTIERREZ |
| Issued | 2/11/2020 | LADBS |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 1/16/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 1/16/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 1/16/2020 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 1/16/2020 | GEORGE SUCHAND |
| Miscellaneous | Cleared | 1/16/2020 | JOE LUCKEY |
| Sewer availability | Cleared | 1/16/2020 | ERIK BEASLEY |
| ZA Case | Cleared | 1/16/2020 | JOE LUCKEY |
| Low Impact Development | Cleared | 1/23/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/23/2020 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 1/31/2020 | RONALD ALLEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kwon,, Ohsung; Lic. No.: C85429 | 1971 ASCOT DR UNIT B MORAGA, CA 94556 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/6/2020 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/7/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/22/2020 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 4/28/2020 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 5/8/2020 | Partial Inspection | DONALD SUNSERI |
| Underground Mechanical | 5/11/2020 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 7/24/2020 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 9/21/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 9/21/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 9/21/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/1/2020 | Approved | TROY SANDERS |
| Green Building Rough | 10/1/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/27/2020 | Approved | TROY SANDERS |
| Shower Pan | 10/27/2020 | Approved | TROY SANDERS |
| Insulation | 11/20/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 12/2/2020 | Approved | TROY SANDERS |
| Final | 12/22/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 12/22/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 12/22/2022 | Approved | TROY SANDERS |
| Final | 6/2/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 6/2/2023 | Approved | TROY SANDERS |
| Final | 7/17/2023 | Not Ready for Inspection | TROY SANDERS |