12473 N ADELPHIA AVE 91340

Certificate Information: 12473 N ADELPHIA AVE 91340

Application / Permit
19014-10000-06253
Plan Check / Job No.
B19LA24464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE TO BE CONVERTED (N) ADU WITH ADDITION PER AB 494 AND SB 229
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 11/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 FERNANDO FLORES
Corrections Issued 12/12/2019 FERNANDO FLORES
Quality Review Completed 12/27/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/7/2020 FERNANDO FLORES
Green Plans Picked Up 2/12/2020 APPLICANT
Plan Check Approved 3/4/2020 FERNANDO FLORES
Building Plans Picked Up 4/7/2020 APPLICANT
Issued 9/30/2021 APPLICANT
CofO in Progress 8/31/2023 KEVIN BERBERYAN
Permit Finaled 11/15/2023 RUBEN SALAS
CofO Issued 11/15/2023 RUBEN SALAS
Permit Finaled 11/15/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/31/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/12/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 2/12/2020 GILBERT URREA
Low Impact Development Cleared 2/12/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/12/2020 CELINA MORENO
Sewer availability Cleared 2/12/2020 EMIL KYUPELYAN
Green Code Cleared 3/3/2020 NEGAR NEJAD

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/25/2022 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 4/27/2022 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 4/29/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/29/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 4/29/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 5/17/2022 Not Ready for Inspection JOHN HAYES
Pre-Inspection 5/17/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 5/23/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 9/7/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 9/9/2022 No Access for Inspection ARAM AVEDISIAN
Green Building Rough 9/9/2022 No Access for Inspection ARAM AVEDISIAN
MERV13>=Rough 9/9/2022 No Access for Inspection ARAM AVEDISIAN
PLUMBING-Rough 9/9/2022 No Access for Inspection ARAM AVEDISIAN
Wood Frame 9/9/2022 No Access for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 9/28/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 10/17/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved ARAM AVEDISIAN
HVAC-Rough 10/17/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/17/2022 Approved ARAM AVEDISIAN
Sewer 10/17/2022 Corrections Issued ARAM AVEDISIAN
Sewer 11/21/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/1/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Insulation 12/12/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 12/30/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/30/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/30/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 7/6/2023 Corrections Issued MICHEL ABAJAN
Gas Test 7/6/2023 Approved MICHEL ABAJAN
PLUMBING-Final 7/6/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/21/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 7/21/2023 Not Ready for Inspection THOMAS FINNILA
Final 7/21/2023 Not Ready for Inspection THOMAS FINNILA
Green Building Final 7/21/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 7/21/2023 Not Ready for Inspection THOMAS FINNILA
MERV13>=Final 7/21/2023 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 7/21/2023 Approved THOMAS FINNILA
PLUMBING-Final 7/21/2023 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 7/21/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 8/18/2023 Approved MICHEL ABAJAN
Final 8/18/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 8/18/2023 Approved MICHEL ABAJAN
HVAC-Final 8/18/2023 Approved MICHEL ABAJAN
MERV13>=Final 8/18/2023 Approved MICHEL ABAJAN
PLUMBING-Final 8/18/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/18/2023 Approved MICHEL ABAJAN
Final 8/23/2023 Corrections Issued DAVID ANDERSON
Service/Power Release 8/23/2023 Not Ready for Inspection DAVID ANDERSON
Final 8/30/2023 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 9/21/2023 Approved KEVIN BERBERYAN