2256 N HARWOOD ST 90031

Certificate Information: 2256 N HARWOOD ST 90031

Application / Permit
19014-10000-06238
Plan Check / Job No.
B19LA24422
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY (8'6" x 29'0") ADDITION (246 SF) AND INTERIOR REMODEL AT EXISTING SINGLE FAMILY DWELLING AT FRONT OF LOT
Permit Issued
Issued on 12/3/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 11/15/2019 RACHEL BEYENE
Corrections Issued 11/15/2019 RACHEL BEYENE
Plan Check Approved 11/26/2019 PRANITA SHAH
Issued 12/3/2019 LADBS
CofO in Progress 8/21/2020 ENRIQUE MIRELES
Permit Finaled 10/2/2020 DEROLD HAUFF
CofO Issued 10/2/2020 DEROLD HAUFF
Permit Finaled 10/2/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/19/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/19/2019 EMIL KYUPELYAN
ZI Cleared 11/19/2019 RICHARD REASER
Low Impact Development Cleared 11/26/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/26/2019 ERIK BEASLEY

Contact Information

Contractor Usa General Contractors Inc; Lic. No.: 1044168-B 23036 BRYCE STREET      WOODLAND HILLS, CA 91364
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/17/2019 Corrections Issued AJA COLLAY
Excavation/Setback/Form/Re-Bar 12/19/2019 Not Ready for Inspection AJA COLLAY
Footing/Foundation/Slab 12/20/2019 Approved AJA COLLAY
ELECTRICAL-Rough 2/26/2020 Partial Inspection CHARLES BOGHOSKHAN
HVAC-Rough 2/26/2020 Partial Inspection CHARLES BOGHOSKHAN
PLUMBING-Rough 2/26/2020 Partial Inspection CHARLES BOGHOSKHAN
PLUMBING-Rough 3/2/2020 Partial Inspection CHARLES BOGHOSKHAN
ELECTRICAL-Rough 3/4/2020 Approved CHARLES BOGHOSKHAN
HVAC-Rough 3/4/2020 Approved CHARLES BOGHOSKHAN
PLUMBING-Rough 3/4/2020 Approved CHARLES BOGHOSKHAN
Wood Frame 3/4/2020 Approved CHARLES BOGHOSKHAN
Insulation 3/11/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 3/11/2020 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 3/19/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/7/2020 Partial Approval HAMIK HARTOUNIAN
Shower Pan 4/7/2020 Approved HAMIK HARTOUNIAN
Final 6/29/2020 Not Ready for Inspection DAVID CHAN
SGSOV-Seismic Gas S/O Valve 6/29/2020 SGSOV Not Ready DAVID CHAN
BUILDING-Rough-Frame 8/14/2020 Approved OSVALDO PARAMO
Final 8/14/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 8/14/2020 Approved OSVALDO PARAMO
Green Building Rough 8/14/2020 Approved OSVALDO PARAMO
MERV13>=Final 8/14/2020 Approved OSVALDO PARAMO
MERV13>=Rough 8/14/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/14/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 8/14/2020 Not Ready for Inspection OSVALDO PARAMO
Final 8/20/2020 Corrections Issued ENRIQUE MIRELES
Pre-Inspection 8/20/2020 Approved ENRIQUE MIRELES
Final 8/24/2020 OK to Issue CofO ENRIQUE MIRELES
Smoke Detectors 8/24/2020 Approved ENRIQUE MIRELES