1474 N SILVER LAKE BLVD 90026
Certificate Information: 1474 N SILVER LAKE BLVD 90026
- Application / Permit
- 19014-10000-06222
- Plan Check / Job No.
- B19LA24375
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to side of (E) SFD. All works per Wood Frame Prescriptive Provisions
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2019 | HELEN NGUYEN |
| Corrections Issued | 11/15/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/26/2019 | MONICA RAMIREZ |
| Plan Check Approved | 12/20/2019 | ARSALAN SHABESTARI |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 9/3/2020 | RUBEN SALAS |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 11/22/2019 | ELAINE LEI |
| Sewer availability | Cleared | 11/22/2019 | ELAINE LEI |
| Grading Pre-Inspection | Cleared | 11/25/2019 | PATRICK MISCHLICH |
Contact Information
| Contractor | Luxe Remodeling; Lic. No.: 993473-B | 329 N WETHERLY DRIVE #205 BEVERLY HILLS, CA 90211 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/9/2020 | Approved | AJA COLLAY |
| Deputy Drilled-In Anchors | 1/31/2020 | Approved | ELMER BLAND |
| Footing/Foundation/Slab | 1/31/2020 | Approved | AJA COLLAY |
| BUILDING-Rough-Frame | 2/12/2020 | Approved | AJA COLLAY |
| ELECTRICAL-Rough | 2/12/2020 | Approved | AJA COLLAY |
| Green Building Rough | 2/12/2020 | Approved | AJA COLLAY |
| Insulation | 2/12/2020 | Approved | AJA COLLAY |
| Wood Frame | 2/21/2020 | Partial Inspection | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 3/6/2020 | Approved | DANNY TOLENTINO |
| Drywall Nailing | 3/13/2020 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Drywall Nailing | 3/17/2020 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/26/2020 | Approved | ROBERT VORHIS |
| Final | 6/26/2020 | Corrections Issued | ROBERT VORHIS |
| Green Building Final | 6/26/2020 | Approved | ROBERT VORHIS |
| HVAC-Final | 6/26/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 6/26/2020 | Approved | ROBERT VORHIS |
| Smoke Detectors | 6/26/2020 | Approved | ROBERT VORHIS |
| Final | 9/2/2020 | OK to Issue CofO | RUBEN SALAS |