2425 S BOONE AVE 90291
Certificate Information: 2425 S BOONE AVE 90291
- Application / Permit
- 19014-10000-06218
- Plan Check / Job No.
- B19LA24360
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of (E) SFD and addition of (N) rear deck on first floor and (N) front deck on second floor.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 11/17/2021
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | HELEN NGUYEN |
| Corrections Issued | 11/25/2019 | HELEN NGUYEN |
| Quality Review Completed | 12/8/2019 | YOUNG KIM |
| Building Plans Picked Up | 12/17/2019 | APPLICANT |
| Applicant returned to address corrections | 3/2/2020 | HELEN NGUYEN |
| Green Plans Picked Up | 4/7/2020 | APPLICANT |
| Plan Check Approved | 6/30/2020 | HELEN NGUYEN |
| Issued | 7/17/2020 | APPLICANT |
| Permit Finaled | 11/5/2021 | DAVID FEILER |
| CofO in Progress | 11/5/2021 | DAVID FEILER |
| No Progress | 11/17/2021 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/24/2019 | TERRI OSBORNE |
| Miscellaneous | Cleared | 12/24/2019 | TERRI OSBORNE |
| Miscellaneous | Cleared | 12/24/2019 | TERRI OSBORNE |
| Specific Plan | Cleared | 3/16/2020 | WESTON PRINGLE |
| Specific Plan | Cleared | 3/16/2020 | WESTON PRINGLE |
| Green Code | Cleared | 4/13/2020 | VIVIAN LAO |
| Specific Plan | Cleared | 4/20/2020 | IRA BROWN |
| Coastal Zone | Cleared | 5/5/2020 | ANNA VIDAL |
Contact Information
| Architect | Lima,, Alberto Pedro; Lic. No.: C21963 | 946 NORTH CRESCENT HEIGHTS BLVD. LOS ANGELES, CA 90046 |
| Contractor | Morpheus Design Inc; Lic. No.: 821748-B | PO BOX 66400 LOS ANGELES, CA 90066 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 8/27/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 8/28/2020 | Partial Approval | DAVID HEINE |
| METHANE-Barrier | 8/28/2020 | Approved | DAVID HEINE |
| METHANE-Subgrade | 8/28/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 10/9/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 10/9/2020 | Approved | DAVID HEINE |
| Sewer | 10/9/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 10/14/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 10/14/2020 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 10/14/2020 | Approved | DAVID HEINE |
| METHANE-Rough | 10/14/2020 | Not Ready for Inspection | DAVID HEINE |
| Shower Pan | 10/14/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 10/20/2020 | Not Ready for Inspection | DAVID HEINE |
| Interior/Exterior Lathing | 10/22/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 10/26/2020 | Approved | DAVID HEINE |
| Green Building Rough | 10/26/2020 | Approved | DAVID HEINE |
| Insulation | 10/26/2020 | Approved | DAVID HEINE |
| METHANE-Rough | 10/26/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 11/4/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 11/4/2020 | Partial Approval | DAVID HEINE |
| Interior/Exterior Lathing | 11/9/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 4/5/2021 | Corrections Issued | JOHNNY MIRANDA |
| Final | 4/5/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/5/2021 | Approved | JOHNNY MIRANDA |
| Green Building Final | 4/5/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 4/5/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 4/5/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/5/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 4/8/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 4/8/2021 | Approved | JOHNNY MIRANDA |
| Green Building Final | 4/12/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/5/2021 | Permit Finaled | DAVID FEILER |
| Service/Power Release | 11/5/2021 | Approved | DAVID FEILER |