2425 S BOONE AVE 90291

Certificate Information: 2425 S BOONE AVE 90291

Application / Permit
19014-10000-06218
Plan Check / Job No.
B19LA24360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel of (E) SFD and addition of (N) rear deck on first floor and (N) front deck on second floor.
Permit Issued
Issued on 7/17/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 11/17/2021

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 HELEN NGUYEN
Corrections Issued 11/25/2019 HELEN NGUYEN
Quality Review Completed 12/8/2019 YOUNG KIM
Building Plans Picked Up 12/17/2019 APPLICANT
Applicant returned to address corrections 3/2/2020 HELEN NGUYEN
Green Plans Picked Up 4/7/2020 APPLICANT
Plan Check Approved 6/30/2020 HELEN NGUYEN
Issued 7/17/2020 APPLICANT
Permit Finaled 11/5/2021 DAVID FEILER
CofO in Progress 11/5/2021 DAVID FEILER
No Progress 11/17/2021 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 12/24/2019 TERRI OSBORNE
Miscellaneous Cleared 12/24/2019 TERRI OSBORNE
Miscellaneous Cleared 12/24/2019 TERRI OSBORNE
Specific Plan Cleared 3/16/2020 WESTON PRINGLE
Specific Plan Cleared 3/16/2020 WESTON PRINGLE
Green Code Cleared 4/13/2020 VIVIAN LAO
Specific Plan Cleared 4/20/2020 IRA BROWN
Coastal Zone Cleared 5/5/2020 ANNA VIDAL

Contact Information

Architect Lima,, Alberto Pedro; Lic. No.: C21963 946 NORTH CRESCENT HEIGHTS BLVD.      LOS ANGELES, CA 90046
Contractor Morpheus Design Inc; Lic. No.: 821748-B PO BOX 66400      LOS ANGELES, CA 90066
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 8/27/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 8/28/2020 Partial Approval DAVID HEINE
METHANE-Barrier 8/28/2020 Approved DAVID HEINE
METHANE-Subgrade 8/28/2020 Approved DAVID HEINE
ELECTRICAL-Rough 10/9/2020 Approved DAVID HEINE
PLUMBING-Rough 10/9/2020 Approved DAVID HEINE
Sewer 10/9/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 10/14/2020 Partial Approval DAVID HEINE
Green Building Rough 10/14/2020 Not Ready for Inspection DAVID HEINE
HVAC-Rough 10/14/2020 Approved DAVID HEINE
METHANE-Rough 10/14/2020 Not Ready for Inspection DAVID HEINE
Shower Pan 10/14/2020 Approved DAVID HEINE
Interior/Exterior Lathing 10/20/2020 Not Ready for Inspection DAVID HEINE
Interior/Exterior Lathing 10/22/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 10/26/2020 Approved DAVID HEINE
Green Building Rough 10/26/2020 Approved DAVID HEINE
Insulation 10/26/2020 Approved DAVID HEINE
METHANE-Rough 10/26/2020 Approved DAVID HEINE
Drywall Nailing 11/4/2020 Approved DAVID HEINE
Interior/Exterior Lathing 11/4/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 11/9/2020 Approved DAVID HEINE
ELECTRICAL-Final 4/5/2021 Corrections Issued JOHNNY MIRANDA
Final 4/5/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 4/5/2021 Approved JOHNNY MIRANDA
Green Building Final 4/5/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Final 4/5/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 4/5/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/5/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 4/5/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 4/8/2021 Approved JOHNNY MIRANDA
HVAC-Final 4/8/2021 Approved JOHNNY MIRANDA
Green Building Final 4/12/2021 Approved JOHNNY MIRANDA
Final 11/5/2021 Permit Finaled DAVID FEILER
Service/Power Release 11/5/2021 Approved DAVID FEILER