6373 W 84TH PL 90045

Certificate Information: 6373 W 84TH PL 90045

Application / Permit
19014-10000-06194
Plan Check / Job No.
B19LA24277
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1ST FLOOR ADDITION AND REMODEL OF KITCHEN TO (E) TWO STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/28/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 KEVIN MORALES
Corrections Issued 11/25/2019 KEVIN MORALES
Quality Review Completed 12/8/2019 YOUNG KIM
Building Plans Picked Up 12/10/2019 APPLICANT
Plan Check Approved 1/28/2020 KEVIN MORALES
Issued 1/28/2020 LADBS
Permit Finaled 8/17/2024 RICHARD STEINBACH
CofO Issued 8/17/2024 RICHARD STEINBACH
Permit Finaled 8/17/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 12/17/2019 CELINA MORENO
Green Code Cleared 12/31/2019 VIVIAN LAO
Miscellaneous Cleared 1/9/2020 KIT AWAKUNI

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2020 Conditional Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval DAVID HEINE
Insulation 2/24/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 3/23/2020 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 3/23/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/23/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 3/25/2020 Conditional Approval JOHNNY MIRANDA
HVAC-Rough 3/25/2020 Approved JOHNNY MIRANDA
Insulation 3/25/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/25/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 3/25/2020 Approved JOHNNY MIRANDA
Drywall Nailing 3/31/2020 Approved JOHNNY MIRANDA
Green Building Rough 3/31/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 4/15/2020 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 4/16/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/18/2020 Conditional Approval JUAN VALENZUELA
Final 8/18/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 8/18/2020 Corrections Issued JUAN VALENZUELA
Green Building Final 8/18/2020 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/18/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 8/18/2020 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 8/20/2020 Approved JUAN VALENZUELA
Final 8/20/2020 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 8/20/2020 Approved JUAN VALENZUELA
Green Building Final 8/20/2020 Approved JUAN VALENZUELA
Smoke Detectors 8/20/2020 Approved JUAN VALENZUELA
Final 9/2/2020 Conditional Approval JUAN VALENZUELA