11031 N NASSAU AVE 91040
Certificate Information: 11031 N NASSAU AVE 91040
- Application / Permit
- 19014-10000-06183
- Plan Check / Job No.
- B19LA24256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE-STORY ADDITION TO THE REAR OF (E) SFD (10'-0" X 12'-1") AND REMOVE EXISTING 10'-0" X 16'-0" PATIO COVER ATTACHED TO (E) SFD AT THE REAR. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 11/14/2019 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 11/14/2019 | CRISTINA SALAZAR |
| Plan Check Approved | 1/14/2020 | CRISTINA SALAZAR |
| No Progress | 1/15/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 1/15/2020 | CRISTINA SALAZAR |
| Issued | 1/23/2020 | LADBS |
| CofO in Progress | 12/31/2020 | MATTHEW NELSON |
| Permit Finaled | 10/6/2021 | MICHAEL SMITH |
| CofO Issued | 10/6/2021 | MICHAEL SMITH |
| Permit Finaled | 10/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | ZIXUAN CHEN |
| Grading Pre-Inspection | Cleared | 11/14/2019 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | JEANIE LAM |
Contact Information
| Contractor | Kendrick Construction; Lic. No.: 438022-B | P O BOX 220697 NEWHALL, CA 91322 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/29/2020 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/29/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/20/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 2/20/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/20/2020 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/19/2020 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/15/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/15/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/15/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/15/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/22/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/22/2020 | Approved | MATTHEW NELSON |
| Insulation | 4/22/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/22/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/29/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/31/2020 | Approved | MATTHEW NELSON |
| Final | 12/31/2020 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 12/31/2020 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/31/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/31/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/31/2020 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/31/2020 | Approved | MATTHEW NELSON |