4840 E MALTA ST 90042

Certificate Information: 4840 E MALTA ST 90042

Application / Permit
19014-10000-06151
Plan Check / Job No.
B19LA24126
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1) ADDITION OF BEDROOM AND REMODEL OF (E) 2-BED/ 1-BATH AND ADD (1) BED & (1) BATH TO EXISTING SFD . 1 OF 2
Permit Issued
Issued on 2/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 ARSALAN SHABESTARI
Corrections Issued 11/25/2019 ARSALAN SHABESTARI
Quality Review Completed 12/7/2019 YOUNG KIM
Building Plans Picked Up 12/10/2019 APPLICANT
Green Plans Picked Up 12/10/2019 APPLICANT
Plan Check Approved 2/14/2020 ARSALAN SHABESTARI
Issued 2/14/2020 LADBS
CofO in Progress 8/5/2020 OSVALDO PARAMO
Permit Finaled 9/1/2020 DEROLD HAUFF
CofO Issued 9/1/2020 DEROLD HAUFF
Permit Finaled 9/1/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/10/2019 ELENA LOPEZ
Grading Pre-Inspection Cleared 12/10/2019 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 12/10/2019 ELENA LOPEZ
Sewer availability Cleared 12/10/2019 ELENA LOPEZ
Specific Plan Cleared 1/30/2020 OLGA RUANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/20/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/18/2020 Corrections Issued OSVALDO PARAMO
Green Building Rough 3/18/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/24/2020 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 3/24/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/2/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 4/7/2020 No Access for Inspection OSVALDO PARAMO
Wood Frame 4/7/2020 No Access for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/13/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/15/2020 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/15/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 4/30/2020 Approved OSVALDO PARAMO
HVAC-Rough 4/30/2020 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 4/30/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/4/2020 Approved OSVALDO PARAMO
Green Building Rough 5/4/2020 Approved OSVALDO PARAMO
HVAC-Rough 5/4/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/4/2020 Partial Approval OSVALDO PARAMO
Insulation 5/7/2020 Partial Approval THOMAS LOGRASSO
Shower Pan 5/7/2020 Approved THOMAS LOGRASSO
Drywall Nailing 5/14/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/3/2020 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 6/23/2020 Approved OSVALDO PARAMO
Footing/Foundation/Slab 6/23/2020 Approved OSVALDO PARAMO
HVAC-Final 6/23/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 6/23/2020 Partial Inspection OSVALDO PARAMO
Final 7/27/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 7/27/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/27/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 7/27/2020 Approved OSVALDO PARAMO
HVAC-Final 7/31/2020 Approved ROBERT VORHIS
PLUMBING-Final 7/31/2020 Approved ROBERT VORHIS
Final 8/4/2020 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Approved OSVALDO PARAMO