8501 W BRIER DR 90046
Certificate Information: 8501 W BRIER DR 90046
- Application / Permit
- 19014-10000-06057
- Plan Check / Job No.
- B19LA23751
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO A SINGLE FAMILY HOME REMODEL OF KITCHEN DINNING & LIVING AREA NEW BASEMENT WALL ASSOCIATED PLUMBING, ELECT, & STRUCTRUAL. " COMPLY WITH DEPARTMRNT ORDER EFFECTIVE DATE 09/10/2019, PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE, CEIS CASE NUMBER IS 879668.
- Permit Issued
- Issued on 7/9/2020
- Issuing Office
- Current Status
- CofO Issued on 5/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | TSE MING HUANG |
| Green Plans Picked Up | 11/22/2019 | APPLICANT |
| Corrections Issued | 12/9/2019 | TSE MING HUANG |
| Quality Review Completed | 12/14/2019 | STANLEY RAAP |
| Applicant returned to address corrections | 12/31/2019 | TSE MING HUANG |
| Plans on Hold | 6/1/2020 | TSE MING HUANG |
| Hold Released | 6/4/2020 | TSE MING HUANG |
| Plan Check Approved | 6/15/2020 | TSE MING HUANG |
| Building Plans Picked Up | 6/26/2020 | APPLICANT |
| Issued | 7/9/2020 | APPLICANT |
| CofO in Progress | 4/12/2021 | GORDON ZUBER |
| Permit Finaled | 5/4/2021 | DANIEL SANCHEZ |
| CofO Issued | 5/4/2021 | DANIEL SANCHEZ |
| Permit Finaled | 5/4/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/31/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 1/31/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 1/31/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/31/2020 | ERIK BEASLEY |
| Green Code | Cleared | 2/25/2020 | VIVIAN LAO |
| BHO/Hillside ordinance | Cleared | 6/8/2020 | TSE MING HUANG |
| Grading Pre-Inspection | Cleared | 6/8/2020 | TSE MING HUANG |
Contact Information
| Architect | Santillan,, Michael; Lic. No.: C23337 | 832 SANTIAGO ROAD COSTA MESA, CA 92626 |
| Contractor | Owner-Builder | , |
| Engineer | Ghazlani,, Andy A; Lic. No.: C60867 | 1021 E CARSON ST 5 LONG BEACH, CA 90807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/22/2020 | Corrections Issued | GORDON ZUBER |
| Deputy Reinf. Concrete | 7/28/2020 | Approved | GORDON ZUBER |
| Footing/Foundation/Slab | 8/18/2020 | Approved | GORDON ZUBER |
| Underground Mechanical | 8/18/2020 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 8/25/2020 | Approved | GORDON ZUBER |
| Footing/Foundation/Slab | 8/25/2020 | Approved | GORDON ZUBER |
| Green Building Rough | 8/25/2020 | Approved | GORDON ZUBER |
| ELECTRICAL-Rough | 9/10/2020 | Not Ready for Inspection | JOHN TCHANG |
| ELECTRICAL-Rough | 9/14/2020 | No Access for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 9/14/2020 | No Access for Inspection | GORDON ZUBER |
| Shower Pan | 9/14/2020 | No Access for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 9/15/2020 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 9/15/2020 | Approved | GORDON ZUBER |
| ELECTRICAL-Rough | 9/17/2020 | Not Ready for Inspection | GORDON ZUBER |
| Insulation | 9/17/2020 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 9/17/2020 | Not Ready for Inspection | GORDON ZUBER |
| Shower Pan | 9/17/2020 | Corrections Issued | GORDON ZUBER |
| Insulation | 9/18/2020 | Approved | GORDON ZUBER |
| Rough-Elec/Plmb/HVAC | 9/18/2020 | Approved | GORDON ZUBER |
| Shower Pan | 9/18/2020 | Not Ready for Inspection | GORDON ZUBER |
| Drywall Nailing | 9/28/2020 | Approved | GORDON ZUBER |
| Interior/Exterior Lathing | 9/28/2020 | Approved | GORDON ZUBER |
| Shower Pan | 9/28/2020 | Approved | GORDON ZUBER |
| ELECTRICAL-Final | 11/9/2020 | Not Ready for Inspection | GORDON ZUBER |
| Gas Test | 11/9/2020 | Approved | GORDON ZUBER |
| HVAC-Final | 11/9/2020 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Final | 11/9/2020 | Not Ready for Inspection | GORDON ZUBER |
| Final | 4/6/2021 | Corrections Issued | GORDON ZUBER |
| Green Building Final | 4/6/2021 | Approved | GORDON ZUBER |
| Reinforced Concrete Frame | 4/6/2021 | Approved | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Approved | GORDON ZUBER |
| Smoke Detectors | 4/6/2021 | Approved | GORDON ZUBER |
| Final | 4/8/2021 | Conditional Approval | GORDON ZUBER |