725 S NORTON AVE 90005
Certificate Information: 725 S NORTON AVE 90005
- Application / Permit
- 19014-10000-06054
- Plan Check / Job No.
- B19LA23727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) 2-STORY SFD BUILDING AND EXTERIOR ALERATION "COMPLY WITH DEPARTMENT ORDER effective date 06/26/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 8/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 11/18/2019 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 11/22/2019 | APPLICANT |
| Quality Review Completed | 11/23/2019 | YOUNG KIM |
| Building Plans Picked Up | 12/3/2019 | APPLICANT |
| Plan Check Approved | 2/6/2020 | ARSALAN SHABESTARI |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 6/27/2023 | JOHN TCHANG |
| Permit Finaled | 8/1/2023 | DANIEL SANCHEZ |
| CofO Issued | 8/1/2023 | DANIEL SANCHEZ |
| Permit Finaled | 8/1/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| CPC | Cleared | 12/12/2019 | TERRI OSBORNE |
| Roof/Waste drainage to street | Cleared | 12/12/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/12/2019 | THOMAS LANG |
| Green Code | Cleared | 12/13/2019 | VIVIAN LAO |
| HPOZ | Cleared | 1/29/2020 | AMANDA KAINER |
| Miscellaneous | Cleared | 1/29/2020 | AMANDA KAINER |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2020 | JUAN ASHTON |
Contact Information
| Contractor | Crescent Development Group Inc; Lic. No.: 1034384-B | 1320 S BOYLE AVE #B LOS ANGELES, CA 90023 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 9/10/2020 | Approved | JOHN TCHANG |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Not Ready for Inspection | EDDY ARDESSI |
| Excavation/Setback/Form/Re-Bar | 9/18/2020 | Approved | EDDY ARDESSI |
| Footing/Foundation/Slab | 9/18/2020 | Approved | EDDY ARDESSI |
| Deputy Steel/Welding | 10/15/2020 | Approved | EDDY ARDESSI |
| Structural Steel Frame | 10/21/2020 | Corrections Issued | EDDY ARDESSI |
| Structural Steel Frame | 11/9/2020 | Partial Approval | EDDY ARDESSI |
| Interior/Exterior Lathing | 11/25/2020 | Approved | EDDY ARDESSI |
| Pre-Inspection | 2/11/2021 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 10/20/2021 | Not Ready for Inspection | ZEYDI STEWART |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | ZEYDI STEWART |
| BUILDING-Rough-Frame | 10/25/2021 | Corrections Issued | ZEYDI STEWART |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | ZEYDI STEWART |
| BUILDING-Rough-Frame | 11/23/2021 | Corrections Issued | ZEYDI STEWART |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | ZEYDI STEWART |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Special/Order Compliance | 1/14/2022 | Partial Inspection | PIERRE VEGA |
| Wood Frame | 1/14/2022 | Corrections Issued | ZEYDI STEWART |
| Drywall Nailing | 2/2/2022 | Approved | PIERRE VEGA |
| Insulation | 2/2/2022 | Approved | PIERRE VEGA |
| Rough-Elec/Plmb/HVAC | 2/2/2022 | Approved | PIERRE VEGA |
| Wood Frame | 2/2/2022 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 6/22/2023 | Approved | JOHN TCHANG |
| Final | 6/22/2023 | Partial Approval | JOHN TCHANG |
| Green Building Final | 6/22/2023 | Approved | JOHN TCHANG |
| Green Building Rough | 6/22/2023 | Approved | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 6/22/2023 | Approved | JOHN TCHANG |