219 E 81ST ST 90003

Certificate Information: 219 E 81ST ST 90003

Application / Permit
19014-10000-06050
Plan Check / Job No.
B19LA23716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING TO CREATE MASTER BEDROOM AND FAMILY ROOM AND LAUNDRY CLOSET. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
Permit Issued
Issued on 11/15/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 8/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 11/6/2019 KEVIN MORALES
Corrections Issued 11/6/2019 KEVIN MORALES
Plan Check Approved 11/15/2019 KEVIN MORALES
Issued 11/15/2019 LADBS
CofO in Progress 8/24/2020 FREDDIE RIVERA
Permit Finaled 8/25/2020 DEROLD HAUFF
CofO Issued 8/25/2020 DEROLD HAUFF
Permit Finaled 8/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/6/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 11/6/2019 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/4/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/11/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 4/7/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 4/7/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/30/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/15/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/15/2020 Approved EUGENE CASSIDY
Green Building Rough 5/15/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 5/15/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/19/2020 Conditional Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Approved BRIAN CHRISTIAN
Green Building Rough 5/19/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 5/27/2020 Approved EUGENE CASSIDY
Insulation 5/27/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/27/2020 Approved EUGENE CASSIDY
Drywall Nailing 6/2/2020 Approved BRIAN CHRISTIAN
Shower Pan 6/24/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 6/29/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 7/22/2020 Approved JOSEPH MCGARRY
Final 7/22/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 7/22/2020 Approved JOSEPH MCGARRY
Green Building Final 7/22/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 7/22/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 8/4/2020 Approved FREDDIE RIVERA
Final 8/4/2020 Conditional Approval FREDDIE RIVERA
PLUMBING-Final 8/4/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Approved FREDDIE RIVERA
Final 8/24/2020 OK to Issue CofO FREDDIE RIVERA