13517 W WINGO ST 91331
Certificate Information: 13517 W WINGO ST 91331
- Application / Permit
- 19014-10000-05977
- Plan Check / Job No.
- B19LA23376
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO SFD ADDITION & PROPOSE (N) COVERED FRONT PORCH & (N) CARPORT & REMODEL (E) SFD
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | FERNANDO FLORES |
| Corrections Issued | 11/27/2019 | FERNANDO FLORES |
| Green Plans Picked Up | 12/6/2019 | APPLICANT |
| Quality Review Completed | 12/19/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 12/24/2019 | APPLICANT |
| Plan Check Approved | 1/13/2020 | FERNANDO FLORES |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 5/26/2022 | GREGG CUMMINGS |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 12/30/2019 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 1/10/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/10/2020 | ELAINE LEI |
| Sewer availability | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| Zoning Information File | Cleared | 1/13/2020 | FERNANDO FLORES |
Contact Information
| Contractor | Tapia Construction Inc; Lic. No.: 981496-B | 7816 TAMPA AVENUE RESEDA, CA 91335 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2020 | Partial Inspection | WILLIAM KUEHN |
| Deputy Wood Construction | 2/5/2020 | Conditional Approval | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 2/6/2020 | Not Ready for Inspection | BEAU COLLINS |
| Rough-Elec/Plmb/HVAC | 2/6/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/11/2020 | Approved | WILLIAM KUEHN |
| Green Building Final | 2/11/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 2/11/2020 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 2/11/2020 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 2/11/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 2/18/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 2/18/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 2/18/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 2/18/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 3/6/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 4/21/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 4/21/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2020 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 4/21/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 5/26/2022 | Approved | GREGG CUMMINGS |
| Final | 5/26/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 5/26/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 5/26/2022 | Approved | GREGG CUMMINGS |