5132 E LINCOLN AVE 90042
Certificate Information: 5132 E LINCOLN AVE 90042
- Application / Permit
- 19014-10000-05975
- Plan Check / Job No.
- B19LA23373
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY ADDITION WITH BALCONY OF 60 SF TO (E) ONE-STORY SFD. NEW DIMENSION OF TWO-STORY SFD IS 50'-2"X26'-7". ADD (N) DECK AT REAR OUTSIDE OF 1ST FLOOR. REDUCE (E) ENTRY PORCH TO 60 SF. REMODEL (E) SFD. 2 OF 2
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 12/31/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 1/14/2020 | KESETE HAREGOT |
| Green Plans Picked Up | 1/22/2020 | APPLICANT |
| Applicant returned to address corrections | 2/10/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 3/2/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 3/8/2021 | CHUNG-WEN CHUANG |
| Issued | 3/23/2021 | APPLICANT |
| Building Plans Picked Up | 3/26/2021 | APPLICANT |
| CofO in Progress | 3/1/2023 | CRAIG VAUGHAN |
| Permit Finaled | 3/4/2023 | DEROLD HAUFF |
| CofO Issued | 3/4/2023 | DEROLD HAUFF |
| Permit Finaled | 3/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 3/9/2020 | CHUNG-WEN CHUANG |
| Low Impact Development | Cleared | 9/11/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 12/30/2020 | JEREMY CARTER |
| GPI Written Notices | Cleared | 3/4/2021 | CHUNG-WEN CHUANG |
| Grading Pre-Inspection | Cleared | 3/4/2021 | CHUNG-WEN CHUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/26/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/26/2021 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 5/26/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 5/27/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 6/16/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 6/16/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Approved | CRAIG VAUGHAN |
| Gas Test | 9/29/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/29/2021 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 9/29/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Shower Pan | 10/8/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/15/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/15/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 10/15/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/15/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/4/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 11/4/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 11/4/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/9/2021 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 11/9/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 12/8/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 12/16/2021 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 12/16/2021 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 1/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/9/2022 | Corrections Issued | CRAIG VAUGHAN |
| Sewer | 2/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/9/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 4/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/21/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 4/21/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 4/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 4/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/21/2022 | Approved | CRAIG VAUGHAN |
| Final | 1/13/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 1/13/2023 | Approved | CRAIG VAUGHAN |
| Final | 2/28/2023 | OK to Issue CofO | CRAIG VAUGHAN |