2618 S HALM AVE 90034
Certificate Information: 2618 S HALM AVE 90034
- Application / Permit
- 19014-10000-05944
- Plan Check / Job No.
- B19LA23256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SECOND STORY ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/9/2020
- Issuing Office
- Current Status
- CofO Issued on 12/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | LAMAR DAVIS |
| Corrections Issued | 12/9/2019 | EVERARDO SANTOS |
| Quality Review Completed | 12/10/2019 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 12/23/2019 | APPLICANT |
| Green Plans Picked Up | 7/22/2020 | APPLICANT |
| Plan Check Approved | 9/4/2020 | LAMAR DAVIS |
| Issued | 9/9/2020 | APPLICANT |
| CofO in Progress | 2/4/2021 | EVAN COOPER |
| Permit Finaled | 12/14/2021 | KENNETH NAGLE |
| CofO Issued | 12/14/2021 | KENNETH NAGLE |
| Permit Finaled | 12/14/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 1/3/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/3/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 7/16/2020 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 7/20/2020 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/15/2020 | Conditional Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 9/16/2020 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/22/2020 | Approved | EVAN COOPER |
| Wood Frame | 10/8/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 11/6/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 11/6/2020 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 11/6/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 11/6/2020 | Corrections Issued | EVAN COOPER |
| MERV13>=Rough | 11/6/2020 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 11/6/2020 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 11/16/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 11/16/2020 | Approved | EVAN COOPER |
| Green Building Rough | 11/16/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 11/16/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/16/2020 | Partial Approval | EVAN COOPER |
| MERV13>=Rough | 11/16/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 11/16/2020 | Approved | EVAN COOPER |
| Insulation | 11/19/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 11/24/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/8/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/22/2021 | SGSOV Not Ready | EVAN COOPER |
| ELECTRICAL-Final | 1/25/2021 | Approved | EVAN COOPER |
| Final | 1/25/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 1/25/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/25/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 2/4/2021 | Approved | EVAN COOPER |
| Final | 2/4/2021 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 2/4/2021 | Approved | EVAN COOPER |
| HVAC-Final | 2/4/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 2/4/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/4/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/4/2021 | Approved | EVAN COOPER |
| Service/Power Release | 12/10/2021 | Approved | EVAN COOPER |