10751 W VALLEYHEART DR 91604
Certificate Information: 10751 W VALLEYHEART DR 91604
- Application / Permit
- 19014-10000-05904
- Plan Check / Job No.
- B19LA23080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY 31'-3"x17'-4" ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/19/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2019 | GEORGE ALVAREZ |
| Corrections Issued | 11/14/2019 | GEORGE ALVAREZ |
| Plan Check Approved | 12/19/2019 | GEORGE ALVAREZ |
| Issued | 12/19/2019 | LADBS |
| CofO in Progress | 3/26/2021 | THOMAS FINNILA |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
| CofO Issued | 4/17/2021 | MICHAEL SMITH |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/10/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 12/10/2019 | CELINA MORENO |
| Sewer availability | Cleared | 12/10/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | JAMES MORALEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wallace,, Gregory Paul; Lic. No.: S3308 | 45 CLARENDON AVE SAN FRANCISCO, CA 94114 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2020 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 2/6/2020 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/19/2020 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 2/19/2020 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 2/19/2020 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/5/2020 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 3/5/2020 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 3/5/2020 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/11/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 3/11/2020 | Approved | JEFFREY PARD |
| MERV13>=Rough | 3/11/2020 | Approved | JEFFREY PARD |
| HVAC-Rough | 3/23/2020 | Approved | JEFFREY PARD |
| Insulation | 3/23/2020 | Approved | JEFFREY PARD |
| Drywall Nailing | 3/31/2020 | Approved | JEFFREY PARD |
| Final | 2/19/2021 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 2/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 3/2/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 3/2/2021 | Approved | THOMAS FINNILA |
| MERV13>=Final | 3/2/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/2/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 3/2/2021 | Approved | THOMAS FINNILA |
| Final | 3/26/2021 | OK to Issue CofO | THOMAS FINNILA |