6952 W 77TH ST 90045

Certificate Information: 6952 W 77TH ST 90045

Application / Permit
19014-10000-05891
Plan Check / Job No.
B19LA23012
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add new 2nd floor to existing garage/carport/rec room on 1st floor for new accessory dwelling unit per AB494 and SB229. Enclose carport on 1st floor to create garage
Permit Issued
Issued on 5/21/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 VU NGUYEN
Corrections Issued 11/13/2019 VU NGUYEN
Quality Review Completed 11/25/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/26/2019 APPLICANT
Applicant returned to address corrections 3/18/2020 VU NGUYEN
Green Plans Picked Up 4/8/2020 APPLICANT
Plan Check Approved 4/14/2020 VU NGUYEN
Issued 5/21/2020 LADBS
CofO in Progress 11/15/2020 JUAN VALENZUELA
CofO Issued 12/8/2020 VINCENT COTTON
Permit Finaled 12/8/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 2/11/2020 JEANETTE VONG
Construction near power lines Cleared 2/26/2020 ERNEST FRESQUEZ
Eng Process Fee Ord 176,300 Cleared 3/4/2020 PAMELA TENEZA
Sewer availability Cleared 3/4/2020 PAMELA TENEZA
CPC Cleared 3/6/2020 SARAHI ORTEGA
CPC Cleared 3/6/2020 SARAHI ORTEGA
CPC Cleared 3/6/2020 SARAHI ORTEGA
Green Code Cleared 4/8/2020 NEGAR NEJAD
Grading Pre-Inspection Cleared 4/14/2020 VU NGUYEN

Contact Information

Contractor N B K Construction; Lic. No.: 987864-B 16738 LAKESHORE DR #H40      LAKE ELSINORE, CA 92530
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2020 Conditional Approval DAVID HEINE
Footing/Foundation/Slab 6/8/2020 Approved JUAN VALENZUELA
METHANE-Barrier 6/8/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 6/8/2020 Approved JUAN VALENZUELA
Underground Mechanical 6/8/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/14/2020 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 7/14/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Rough 7/14/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 7/14/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 7/15/2020 Approved JUAN VALENZUELA
HVAC-Rough 7/15/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/3/2020 Approved JUAN VALENZUELA
Green Building Rough 8/3/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/3/2020 Partial Approval JUAN VALENZUELA
Insulation 8/4/2020 Approved JUAN VALENZUELA
Shower Pan 8/4/2020 Approved JUAN VALENZUELA
Drywall Nailing 8/6/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/20/2020 Approved JUAN VALENZUELA
Pre-Inspection 9/10/2020 Partial Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/7/2020 SGSOV Not Ready JUAN VALENZUELA
Final 10/14/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 11/12/2020 Approved JUAN VALENZUELA
Final 11/12/2020 OK to Issue CofO JUAN VALENZUELA
Green Building Final 11/12/2020 Approved JUAN VALENZUELA
HVAC-Final 11/12/2020 Approved JUAN VALENZUELA
PLUMBING-Final 11/12/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 11/12/2020 Approved JUAN VALENZUELA