6952 W 77TH ST 90045
Certificate Information: 6952 W 77TH ST 90045
- Application / Permit
- 19014-10000-05891
- Plan Check / Job No.
- B19LA23012
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Add new 2nd floor to existing garage/carport/rec room on 1st floor for new accessory dwelling unit per AB494 and SB229. Enclose carport on 1st floor to create garage
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | VU NGUYEN |
| Corrections Issued | 11/13/2019 | VU NGUYEN |
| Quality Review Completed | 11/25/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/26/2019 | APPLICANT |
| Applicant returned to address corrections | 3/18/2020 | VU NGUYEN |
| Green Plans Picked Up | 4/8/2020 | APPLICANT |
| Plan Check Approved | 4/14/2020 | VU NGUYEN |
| Issued | 5/21/2020 | LADBS |
| CofO in Progress | 11/15/2020 | JUAN VALENZUELA |
| CofO Issued | 12/8/2020 | VINCENT COTTON |
| Permit Finaled | 12/8/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2020 | JEANETTE VONG |
| Construction near power lines | Cleared | 2/26/2020 | ERNEST FRESQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 3/4/2020 | PAMELA TENEZA |
| CPC | Cleared | 3/6/2020 | SARAHI ORTEGA |
| CPC | Cleared | 3/6/2020 | SARAHI ORTEGA |
| CPC | Cleared | 3/6/2020 | SARAHI ORTEGA |
| Green Code | Cleared | 4/8/2020 | NEGAR NEJAD |
| Grading Pre-Inspection | Cleared | 4/14/2020 | VU NGUYEN |
Contact Information
| Contractor | N B K Construction; Lic. No.: 987864-B | 16738 LAKESHORE DR #H40 LAKE ELSINORE, CA 92530 |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/29/2020 | Conditional Approval | DAVID HEINE |
| Footing/Foundation/Slab | 6/8/2020 | Approved | JUAN VALENZUELA |
| METHANE-Barrier | 6/8/2020 | Approved | JUAN VALENZUELA |
| METHANE-Subgrade | 6/8/2020 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 6/8/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/14/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 7/14/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Rough | 7/14/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 7/14/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/15/2020 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 7/15/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/3/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/3/2020 | Partial Approval | JUAN VALENZUELA |
| Insulation | 8/4/2020 | Approved | JUAN VALENZUELA |
| Shower Pan | 8/4/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 8/6/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/20/2020 | Approved | JUAN VALENZUELA |
| Pre-Inspection | 9/10/2020 | Partial Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 10/14/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 11/12/2020 | Approved | JUAN VALENZUELA |
| Final | 11/12/2020 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 11/12/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/12/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 11/12/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 11/12/2020 | Approved | JUAN VALENZUELA |