4229 S GRAND VIEW BLVD 90066
Certificate Information: 4229 S GRAND VIEW BLVD 90066
- Application / Permit
- 19014-10000-05833
- Plan Check / Job No.
- B19LA22777
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY ADDITION TO SINGLE FAMILY DWELLING AND CREATE AN (E) ONE-CAR GARAGE INTO A TWO-CAR GARAGE
- Permit Issued
- Issued on 4/1/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 11/14/2019 | SERGIO GUTIERREZ |
| Green Plans Picked Up | 11/18/2019 | APPLICANT |
| Quality Review Completed | 12/2/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 12/3/2019 | APPLICANT |
| Plan Check Approved | 3/6/2020 | SERGIO GUTIERREZ |
| Issued | 4/1/2020 | LADBS |
| CofO in Progress | 4/16/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 4/19/2024 | DANIEL ORRANTE |
| CofO Issued | 4/19/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 12/5/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | CELINA MORENO |
| Sewer availability | Cleared | 1/22/2020 | CELINA MORENO |
| Specific Plan | Cleared | 1/22/2020 | COLLINS ALLAN |
| Specific Plan | Cleared | 1/22/2020 | KIT AWAKUNI |
| Hydrant and Access approval | Cleared | 2/6/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 2/11/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 2/14/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/14/2020 | JEANETTE VONG |
Contact Information
| Contractor | Dh Remodel Services; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
| Engineer | Itani,, Riad Hassan; Lic. No.: C55688 | 2459 W 228TH ST TORRANCE, CA 90501 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2020 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 4/24/2020 | Approved | DAVID FEILER |
| Special/Order Compliance | 5/12/2020 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 5/13/2020 | No Access for Inspection | DAVID FEILER |
| Special/Order Compliance | 5/13/2020 | Order to Comply Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 5/19/2020 | Corrections Issued | DAVID FEILER |
| Piling/Pier/Caisson | 5/19/2020 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 5/27/2020 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 6/5/2020 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/5/2020 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 6/5/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 7/24/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 11/4/2020 | Partial Approval | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/2/2020 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/9/2020 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 12/9/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/9/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/11/2021 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 3/16/2021 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 3/19/2021 | Partial Approval | ENRIQUE MIRELES |
| HVAC-Rough | 5/11/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 5/11/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/11/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/19/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 5/19/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/9/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/9/2021 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/27/2021 | Approved | ENRIQUE MIRELES |
| Deck | 5/18/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Gas Test | 10/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 10/10/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Service/Power Release | 10/10/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/17/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 10/17/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/17/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/17/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/17/2023 | Approved | JESUS RODRIGUEZ |
| Final | 3/21/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/21/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 3/21/2024 | Approved | JESUS RODRIGUEZ |
| Final | 3/26/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/15/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 4/15/2024 | Approved | JESUS RODRIGUEZ |