4355 S KENYON AVE 90066
Certificate Information: 4355 S KENYON AVE 90066
- Application / Permit
- 19014-10000-05795
- Plan Check / Job No.
- B19LA22620
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD
- Permit Issued
- Issued on 12/30/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | FERNANDO FLORES |
| Corrections Issued | 11/7/2019 | FERNANDO FLORES |
| Quality Review Completed | 11/19/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 11/22/2019 | APPLICANT |
| Green Plans Picked Up | 11/22/2019 | APPLICANT |
| Applicant returned to address corrections | 12/18/2019 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/23/2019 | FERNANDO FLORES |
| Plan Check Approved | 12/24/2019 | FERNANDO FLORES |
| Issued | 12/30/2019 | LADBS |
| CofO in Progress | 12/1/2020 | KENNETH NAGLE |
| No Progress | 12/1/2020 | KENNETH NAGLE |
| CofO in Progress | 12/2/2020 | PIERRE VEGA |
| Permit Finaled | 12/2/2020 | VINCENT COTTON |
| CofO Issued | 12/2/2020 | VINCENT COTTON |
| Permit Finaled | 12/2/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Green Code | Cleared | 12/17/2019 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 12/23/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/23/2019 | ERIK BEASLEY |
Contact Information
| Contractor | L And N Builders Inc; Lic. No.: 955521-B | 16944 KNAPP STREET NORTHRIDGE, CA 91343 |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2020 | Partial Approval | DAVID FEILER |
| Deputy Reinf. Concrete | 2/4/2020 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 4/15/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 4/15/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 4/28/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 4/30/2020 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 4/30/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/30/2020 | Approved | JOHNNY MIRANDA |
| Shower Pan | 4/30/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/4/2020 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/4/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/4/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 5/4/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/5/2020 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 5/13/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 5/14/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/14/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 9/3/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/3/2020 | Corrections Issued | JOHNNY MIRANDA |
| Service/Power Release | 9/3/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/11/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 9/11/2020 | Approved | JOHNNY MIRANDA |
| Final | 9/11/2020 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/11/2020 | Approved | JOHNNY MIRANDA |
| Green Building Final | 9/11/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 9/11/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/11/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 9/11/2020 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 9/11/2020 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 9/11/2020 | Approved | JOHNNY MIRANDA |
| Final | 9/21/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 9/21/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 9/21/2020 | Approved | JOHNNY MIRANDA |
| Final | 9/24/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 9/24/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 10/9/2020 | No Access for Inspection | DAVID HEINE |
| Green Building Final | 10/9/2020 | No Access for Inspection | DAVID HEINE |
| Final | 11/17/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Final | 11/17/2020 | Approved | JOHNNY MIRANDA |