3441 S ALSACE AVE 90016

Certificate Information: 3441 S ALSACE AVE 90016

Application / Permit
19014-10000-05782
Plan Check / Job No.
B19LA22567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 24' X 16'-9" ADDITION TO (E) 37'-4" X 34'-3" SFD. INCLUDE PARTIAL INTERIOR REMODELLING OF THE EXISTING SFD PER PLAN.
Permit Issued
Issued on 3/11/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 CHUNG-WEN CHUANG
Corrections Issued 11/25/2019 CHUNG-WEN CHUANG
Green Plans Picked Up 11/27/2019 APPLICANT
Quality Review Completed 12/16/2019 KESETE HAREGOT
Building Plans Picked Up 12/19/2019 APPLICANT
Applicant returned to address corrections 1/21/2020 CHUNG-WEN CHUANG
Plan Check Approved 3/5/2020 CHUNG-WEN CHUANG
Issued 3/11/2020 LADBS
CofO in Progress 10/29/2020 DAVID FEILER
Permit Finaled 10/30/2020 DEROLD HAUFF
CofO Issued 10/30/2020 DEROLD HAUFF
Permit Finaled 10/30/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/16/2020 CELINA MORENO
Green Code Cleared 1/16/2020 CHUNG-WEN CHUANG
Sewer availability Cleared 1/16/2020 CELINA MORENO
Low Impact Development Cleared 1/21/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/21/2020 THOMAS LANG

Contact Information

Architect Yung,, Paul H; Lic. No.: C28869 5558 VALERIO TRAIL      SAN DIEGO, CA 92130
Contractor Castillo Construction; Lic. No.: 960211-B 228 GRAND BOULEVARD      VENICE, CA 90291

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2020 Approved MATTHEW NUCKOLLS
ELECTRICAL-Rough 6/22/2020 Approved DAVID CHAN
PLUMBING-Rough 6/22/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 6/23/2020 Corrections Issued DAVID CHAN
HVAC-Rough 6/23/2020 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 6/30/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 6/30/2020 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/1/2020 Approved COREY HUPP
Interior/Exterior Lathing 7/15/2020 Partial Approval SABAS ALONSO
Shower Pan 7/15/2020 Corrections Issued SABAS ALONSO
Green Building Rough 7/20/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/20/2020 Partial Approval SABAS ALONSO
Shower Pan 7/20/2020 Approved SABAS ALONSO
Insulation 7/23/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/23/2020 Approved SABAS ALONSO
Drywall Nailing 7/29/2020 Approved COREY HUPP
BUILDING-Rough-Frame 10/1/2020 Approved OSVALDO PARAMO
Final 10/1/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 10/1/2020 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/1/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/1/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 10/7/2020 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 10/7/2020 Partial Inspection DAVID FEILER
PLUMBING-Rough 10/7/2020 Partial Inspection DAVID FEILER
Final 10/19/2020 Partial Inspection DAVID FEILER
Green Building Final 10/19/2020 Approved DAVID FEILER
PLUMBING-Final 10/19/2020 Approved DAVID FEILER
Final 10/28/2020 OK to Issue CofO DAVID FEILER