1321 N NORMANDIE AVE 90027

Certificate Information: 1321 N NORMANDIE AVE 90027

Application / Permit
19014-10000-05757
Plan Check / Job No.
B19LA22465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BATHROOM ADDITION 3' X 8' (24 SQFT) 1 STORY TO REAR OF SFD. INTERIOR REMODELTO RELOCATION OF (E) KITCHEN TO (E) DEN AND CREATE 3RD BEDROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 12/3/2021
Issuing Office
Current Status
CofO Issued on 8/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2019 APPLICANT
Assigned to Plan Check Engineer 10/22/2019 ADAM HEGAZI
Corrections Issued 10/22/2019 ADAM HEGAZI
Applicant returned to address corrections 8/18/2021 TSE MING HUANG
Applicant returned to address corrections 11/24/2021 ZAW HAN
Plan Check Approved 11/29/2021 ZAW HAN
Issued 12/3/2021 APPLICANT
Building Plans Picked Up 12/6/2021 APPLICANT
CofO in Progress 8/24/2023 JOAQUIN GREENOUGH
Permit Finaled 8/24/2023 DEROLD HAUFF
CofO Issued 8/24/2023 DEROLD HAUFF
Permit Finaled 8/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/21/2021 WALLIE JONG
Sewer availability Cleared 10/21/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/22/2021 WALLIE JONG
Tenant Habitability Plan Cleared 11/4/2021 MICHAEL SOTO

Contact Information

Contractor Diego Victor; Lic. No.: 1048380-B 3267 SANDSTONE CT      PALMDALE, CA 93551

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/18/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 3/31/2022 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 3/31/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 3/31/2022 Partial Inspection RUBEN SALAS
Pre-Inspection 5/17/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/8/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 11/1/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 11/1/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/17/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 11/17/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 11/17/2022 Approved JOAQUIN GREENOUGH
Wood Frame 11/17/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/20/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 12/20/2022 Corrections Issued JOAQUIN GREENOUGH
Insulation 12/20/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 12/20/2022 Approved JOAQUIN GREENOUGH
Wood Frame 12/20/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/30/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 12/30/2022 Approved STUART CHAPMAN
Green Building Rough 12/30/2022 Approved STUART CHAPMAN
HVAC-Rough 1/9/2023 Approved JOAQUIN GREENOUGH
Insulation 1/9/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 2/27/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/17/2023 Approved JOAQUIN GREENOUGH
Final 8/17/2023 Partial Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/17/2023 Approved JOAQUIN GREENOUGH
Green Building Final 8/17/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 8/17/2023 Approved JOAQUIN GREENOUGH
Final 8/24/2023 OK to Issue CofO JOAQUIN GREENOUGH