10639 S MANHATTAN PL 90047

Certificate Information: 10639 S MANHATTAN PL 90047

Application / Permit
19014-10000-05706
Plan Check / Job No.
B19LA22232
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO SINGLE FAMILY WITH (N) MASTER BEDROOM, MASTER BATHROOM, NEW LAUNDRY RM AND EXTEND (E) BEDROOM
Permit Issued
Issued on 1/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2019 APPLICANT
Assigned to Plan Check Engineer 10/22/2019 SINA KHOSRAVI
Corrections Issued 10/22/2019 SINA KHOSRAVI
Applicant returned to address corrections 12/31/2019 RAHEL BEYENE
Plan Check Approved 1/17/2020 RAHEL BEYENE
Issued 1/17/2020 LADBS
CofO in Progress 12/15/2020 FREDDIE RIVERA
Permit Finaled 12/24/2020 DEROLD HAUFF
CofO Issued 12/24/2020 DEROLD HAUFF
Permit Finaled 12/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 12/31/2019 CELINA MORENO
Sewer availability Cleared 1/17/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Liu,, Hue Cam; Lic. No.: C66754 10732 LA BATISTA AVENUE      FOUNTAIN VALLEY, CA 92708

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2020 Approved HORACE FULTZ
METHANE-Barrier 2/26/2020 Approved HORACE FULTZ
METHANE-Subgrade 2/26/2020 Approved HORACE FULTZ
BUILDING-Rough-Frame 3/12/2020 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 3/12/2020 Partial Approval FREDDIE RIVERA
Deck 3/23/2020 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Approved HORACE FULTZ
ELECTRICAL-Rough 4/27/2020 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval FREDDIE RIVERA
HVAC-Rough 4/27/2020 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 4/27/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 5/7/2020 Conditional Approval SCOTT FINNILA
Wood Frame 5/7/2020 Conditional Approval SCOTT FINNILA
Insulation 5/11/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 5/11/2020 Partial Approval SABAS ALONSO
Drywall Nailing 5/21/2020 Partial Approval SABAS ALONSO
Green Building Rough 5/21/2020 Approved SABAS ALONSO
PLUMBING-Rough 5/29/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 10/23/2020 Approved FREDDIE RIVERA
Drywall Nailing 10/23/2020 Approved FREDDIE RIVERA
Final 10/23/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 10/23/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 10/23/2020 Not Ready for Inspection FREDDIE RIVERA
Final 12/14/2020 OK to Issue CofO FREDDIE RIVERA
Smoke Detectors 12/14/2020 Approved FREDDIE RIVERA