3409 N OAK GLEN DR 90068
Certificate Information: 3409 N OAK GLEN DR 90068
- Application / Permit
- 19014-10000-05688
- Plan Check / Job No.
- B19LA22172
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 320 SF AT THE REAR AND GARAGE CONVERSION INTO BEDROOM AND LAUNDRY AND CONVERT COVERED ENTRY TO COVERED CARPORT
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 10/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | JESSE ARELLANO |
| Corrections Issued | 1/13/2020 | JESSE ARELLANO |
| Quality Review Completed | 1/28/2020 | BILL STUTSMAN |
| Applicant returned to address corrections | 4/1/2020 | JESSE ARELLANO |
| Green Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 6/18/2020 | JESSE ARELLANO |
| Plan Check Approved | 6/24/2020 | JESSE ARELLANO |
| Issued | 12/22/2020 | APPLICANT |
| Building Plans Picked Up | 6/9/2021 | APPLICANT |
| CofO in Progress | 10/18/2022 | BRIAN SULLIVAN |
| Permit Finaled | 10/20/2022 | DEROLD HAUFF |
| CofO Issued | 10/20/2022 | DEROLD HAUFF |
| Permit Finaled | 10/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 1/9/2020 | LOURDES RAMIRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/10/2020 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | CELINA MORENO |
| Green Code | Cleared | 3/11/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 5/15/2020 | JORGE MEJIA LEMUS |
| ZI | Cleared | 5/15/2020 | DOMINICK ORTIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Asfour,, Andrew Victor; Lic. No.: C87012 | 6375 BLOSSOM LANE CHINO HILLS, CA 91709 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/24/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 3/17/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| MERV13>=Rough | 3/17/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/9/2021 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 4/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| MERV13>=Rough | 4/20/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/20/2021 | Partial Approval | BRIAN SULLIVAN |
| Wood Frame | 4/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/29/2021 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 4/29/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/29/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/29/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 5/11/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 5/11/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/11/2021 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 5/11/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/2/2022 | Approved | BRIAN SULLIVAN |
| Final | 3/2/2022 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/2/2022 | Approved | BRIAN SULLIVAN |
| Green Building Final | 3/2/2022 | Approved | BRIAN SULLIVAN |
| MERV13>=Final | 3/2/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 3/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 4/29/2022 | Conditional Approval | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 4/29/2022 | Approved | BRIAN SULLIVAN |