2924 S BENTLEY AVE 90064
Certificate Information: 2924 S BENTLEY AVE 90064
- Application / Permit
- 19014-10000-05629
- Plan Check / Job No.
- B19LA21942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADDITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB 449 AND SB 229
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | SINA KHOSRAVI |
| Corrections Issued | 10/17/2019 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/6/2019 | RAHEL BEYENE |
| Plan Check Approved | 2/4/2020 | KEVIN MORALES |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 4/28/2022 | KENNETH NAGLE |
| Permit Finaled | 4/28/2022 | DANIEL ORRANTE |
| CofO Issued | 4/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Grading Pre-Inspection | Cleared | 10/17/2019 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Construction near power lines | Cleared | 11/27/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/27/2019 | RIDWAN HARDY |
Contact Information
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| PLUMBING-Rough | 3/2/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| Pre-Inspection | 3/2/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 3/16/2020 | Approved | KEVIN BEAULIEU |
| Special/Order Compliance | 4/20/2020 | Partial Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/2/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 6/2/2020 | Not Ready for Inspection | KENNETH NAGLE |
| MERV13>=Rough | 6/2/2020 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 6/2/2020 | Approved | KENNETH NAGLE |
| Sewer | 6/2/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/26/2020 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 6/26/2020 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/1/2020 | Partial Approval | JUSTIN CURTIS |
| ELECTRICAL-Rough | 7/1/2020 | Approved | JUSTIN CURTIS |
| Green Building Rough | 7/1/2020 | Approved | JUSTIN CURTIS |
| MERV13>=Rough | 7/1/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| PLUMBING-Rough | 7/1/2020 | Approved | JUSTIN CURTIS |
| Insulation | 8/11/2020 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/18/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/18/2020 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 9/3/2020 | Approved | KEVIN SARGSYAN |
| Special/Order Compliance | 6/22/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Posting Pre-Inspection | 6/30/2021 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Rec and Parks Fee Memo | 6/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 9/21/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 1/21/2022 | Corrections Issued | JOHNNY MIRANDA |
| Final | 1/21/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 1/21/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 1/21/2022 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Final | 1/21/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Rough | 1/21/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 1/21/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 1/21/2022 | Approved | JOHNNY MIRANDA |
| Final | 4/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Final | 4/15/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | JOHNNY MIRANDA |