3163 1/2 S HELMS AVE 90034

Certificate Information: 3163 1/2 S HELMS AVE 90034

Application / Permit
19014-10000-05604
Plan Check / Job No.
B19LA21840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH (N) ADDITION TO ACCESSORY DWELLING UNIT PER AB494 AND SB229.
Permit Issued
Issued on 1/10/2020
Issuing Office
West Los Angeles
Current Status
Issued on 1/10/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Assigned to Plan Check Engineer 10/18/2019 MONICA RAMIREZ
Corrections Issued 10/21/2019 MONICA RAMIREZ
Plan Check Approved 1/6/2020 JESSE JIMENEZ
Issued 1/10/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 10/18/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/18/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 10/18/2019 THOMAS LANG
Sewer availability Cleared 11/5/2019 THOMAS LANG
Community Plan Implem. Overlay Cleared 11/6/2019 KYLE WINSTON
ZI Cleared 11/6/2019 KYLE WINSTON
Construction near power lines Cleared 12/23/2019 RIDWAN HARDY
Construction within easement Cleared 12/23/2019 RIDWAN HARDY

Contact Information

Contractor Lozano Construction Inc; Lic. No.: 968956-B 3937 W. 105TH ST.      INGLEWOOD, CA 90303
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/13/2020 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 2/13/2020 Corrections Issued EVAN COOPER
PLUMBING-Rough 2/13/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 2/27/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 2/27/2020 Partial Approval EVAN COOPER
Footing/Foundation/Slab 2/28/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Approved RONALD WEBER
ELECTRICAL-Rough 4/20/2020 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/20/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/20/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Service/Power Release 4/20/2020 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 4/20/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/24/2020 Approved OGANES TARAKHCHYAN
Wood Frame 4/24/2020 Approved OGANES TARAKHCHYAN
Insulation 4/29/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 4/29/2020 Approved EVAN COOPER
Rough-Elec/Plmb/HVAC 4/29/2020 Approved EVAN COOPER
Drywall Nailing 5/6/2020 Approved EVAN COOPER
Gas Test 6/2/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/8/2020 Not Ready for Inspection JUSTIN CURTIS
Final 7/8/2020 Corrections Issued JUSTIN CURTIS
Green Building Final 7/8/2020 Not Ready for Inspection JUSTIN CURTIS
Green Building Rough 7/8/2020 Not Ready for Inspection JUSTIN CURTIS
MERV13>=Final 7/8/2020 Not Ready for Inspection JUSTIN CURTIS
MERV13>=Rough 7/8/2020 Not Ready for Inspection JUSTIN CURTIS
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV Not Ready JUSTIN CURTIS
Smoke Detectors 7/8/2020 Not Ready for Inspection JUSTIN CURTIS
ELECTRICAL-Final 7/9/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Final 7/9/2020 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/13/2020 Partial Approval JUSTIN CURTIS
Final 7/13/2020 Not Ready for Inspection JUSTIN CURTIS
Green Building Final 7/13/2020 Not Ready for Inspection JUSTIN CURTIS
Green Building Rough 7/13/2020 Not Ready for Inspection JUSTIN CURTIS
MERV13>=Final 7/13/2020 Not Ready for Inspection JUSTIN CURTIS
MERV13>=Rough 7/13/2020 Not Ready for Inspection JUSTIN CURTIS
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Not Ready JUSTIN CURTIS
Service/Power Release 7/13/2020 Not Ready for Inspection JUSTIN CURTIS
Smoke Detectors 7/13/2020 Approved JUSTIN CURTIS