12109 W CHARNOCK ROAD 90066

Certificate Information: 12109 W CHARNOCK ROAD 90066

Application / Permit
19014-10000-05572
Plan Check / Job No.
B19LA21730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND ADDITION TO AN EXISTING ONE STORY DETACHED 2-CAR GARAGE, TO CREATE AN ACCESSORY DWELLING UNIT PER AB494 AND SB229.
Permit Issued
Issued on 1/16/2020
Issuing Office
Metro
Current Status
CofO Corrected on 2/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 JOHNNY WU
Corrections Issued 11/5/2019 JOHNNY WU
Quality Review Completed 11/19/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/20/2019 APPLICANT
Applicant returned to address corrections 12/6/2019 JOHNNY WU
Applicant returned to address corrections 1/3/2020 JOHNNY WU
Applicant returned to address corrections 1/6/2020 JOHNNY WU
Plan Check Approved 1/16/2020 KESETE HAREGOT
Issued 1/16/2020 LADBS
CofO in Progress 1/16/2021 KENNETH NAGLE
CofO Issued-Status Void 1/16/2021 KENNETH NAGLE
Permit Finaled-Status Void 1/16/2021 KENNETH NAGLE
Re-Activate Permit 2/8/2021 VINCENT COTTON
CofO Corrected 2/22/2021 VINCENT COTTON
Permit Finaled 2/22/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 11/22/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/22/2019 THOMAS LANG
Sewer availability Cleared 11/22/2019 THOMAS LANG
Specific Plan Cleared 11/22/2019 TAIMOUR TANAVOLI
DPI Written Notices Cleared 12/6/2019 JOHNNY WU
GPI Written Notices Cleared 12/6/2019 JOHNNY WU
Low Impact Development Cleared 1/2/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/2/2020 ERIK BEASLEY
Green Code Cleared 1/9/2020 NEGAR NEJAD

Contact Information

Contractor Owner-Builder       ,
Engineer Nastarin,, Hooman; Lic. No.: C62199 554 S SAN VICNETE BLVD 202      LOS ANGELES, CA 90048

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2020 Approved KEVIN BEAULIEU
PLUMBING-Rough 2/14/2020 No Access for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 2/28/2020 Approved KEVIN BEAULIEU
Floor/Roof Diaphrgm/Shear Wall 3/24/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/24/2020 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 4/10/2020 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/10/2020 Not Ready for Inspection DAVID FEILER
Green Building Rough 4/10/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/10/2020 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 4/16/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval OGANES TARAKHCHYAN
Gas Test 4/16/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 4/16/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/16/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/28/2020 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/18/2020 Partial Approval JUSTIN CURTIS
Underground Mechanical 6/25/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/7/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 7/9/2020 Approved JUSTIN CURTIS
HVAC-Rough 7/10/2020 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 7/17/2020 Approved JUSTIN CURTIS
BUILDING-Rough-Frame 7/21/2020 Partial Approval JUSTIN CURTIS
Green Building Rough 7/21/2020 Approved JUSTIN CURTIS
Interior/Exterior Lathing 7/22/2020 Approved JUSTIN CURTIS
Insulation 7/27/2020 Approved EVAN COOPER
Drywall Nailing 8/4/2020 Approved EVAN COOPER
Shower Pan 8/4/2020 Approved EVAN COOPER
Interior/Exterior Lathing 8/14/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 10/19/2020 Corrections Issued EVAN COOPER
Gas Test 10/19/2020 No Access for Inspection EVAN COOPER
PLUMBING-Final 10/19/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Final 10/26/2020 Not Ready for Inspection EVAN COOPER
Green Building Final 10/26/2020 Not Ready for Inspection EVAN COOPER
HVAC-Final 10/26/2020 Partial Approval EVAN COOPER
PLUMBING-Final 10/26/2020 Not Ready for Inspection EVAN COOPER
Smoke Detectors 10/26/2020 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 10/28/2020 Approved EVAN COOPER
Green Building Final 10/28/2020 Approved EVAN COOPER
HVAC-Final 10/28/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 10/28/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 12/7/2020 Approved RICHARD ROBLES
Final 12/7/2020 Conditional Approval RICHARD ROBLES
Footing/Foundation/Slab 12/7/2020 Approved RICHARD ROBLES
HVAC-Final 12/7/2020 Approved RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 12/7/2020 SGSOV Approved RICHARD ROBLES
Smoke Detectors 12/7/2020 Approved RICHARD ROBLES
Service/Power Release 12/29/2020 Approved KENNETH NAGLE
Special/Order Compliance 1/13/2021 Corrections Issued KENNETH NAGLE