11007 W WRIGHTWOOD LANE 91604

Certificate Information: 11007 W WRIGHTWOOD LANE 91604

Application / Permit
19014-10000-05560
Plan Check / Job No.
B19LA21666
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) SINGLE FAMILY DWELLING W/ATT GARAGE, 13'-6" X 34'-0" TRELLIS ADDITION, & SKYLIGHTS
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 1/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 LAMAR DAVIS
Corrections Issued 10/31/2019 LAMAR DAVIS
Quality Review Completed 11/13/2019 HERNAN ARREOLA
Building Plans Picked Up 11/14/2019 APPLICANT
Applicant returned to address corrections 12/5/2019 LAMAR DAVIS
Plan Check Approved 1/10/2020 LAMAR DAVIS
Issued 2/18/2021 APPLICANT
CofO in Progress 12/21/2021 BRIAN SULLIVAN
Permit Finaled 1/14/2022 DEROLD HAUFF
CofO Issued 1/14/2022 DEROLD HAUFF
Permit Finaled 1/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/26/2019 KIRK LINKLATER
Green Code Cleared 12/5/2019 LAMAR DAVIS
Hydrant and Access approval Cleared 12/5/2019 JEREMY CARTER
Specific Plan Cleared 1/7/2020 LIZZI BEDUYA

Contact Information

Architect Callahan,, Charles P; Lic. No.: C36958 2020 CUMMINGS DRIVE      LOS ANGELES, CA 90027
Contractor Perkins Michael Construction; Lic. No.: 745473-B 520 S SUNSET CANYON DRIVE      BURBANK, CA 91501
Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2021 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 2/25/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 4/14/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 4/14/2021 Partial Approval SCOTT FINNILA
HVAC-Rough 4/14/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 4/14/2021 Approved SCOTT FINNILA
Wood Frame 4/14/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 4/23/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 4/23/2021 Approved BRIAN SULLIVAN
HVAC-Rough 4/23/2021 Approved BRIAN SULLIVAN
Drywall Nailing 5/7/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Approved BRIAN SULLIVAN
Insulation 5/7/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 5/7/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 5/13/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/8/2021 Not Ready for Inspection BRIAN SULLIVAN
Shower Pan 6/8/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 7/6/2021 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/28/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/28/2021 Approved BRIAN SULLIVAN
Pre-Inspection 9/28/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 12/13/2021 Not Ready for Inspection BRIAN SULLIVAN
Final 12/13/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 12/13/2021 Approved BRIAN SULLIVAN
HVAC-Final 12/13/2021 Approved BRIAN SULLIVAN
PLUMBING-Final 12/13/2021 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 12/13/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 12/20/2021 Approved BRIAN SULLIVAN
Final 12/20/2021 OK to Issue CofO BRIAN SULLIVAN
Smoke Detectors 12/20/2021 Approved BRIAN SULLIVAN