173 N CARMELINA AVE 90049
Certificate Information: 173 N CARMELINA AVE 90049
- Application / Permit
- 19014-10000-05555
- Plan Check / Job No.
- B19LA21619
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SINGLE FAMILY RESIDENCE ADDITION & REMODEL. GROUND FLOOR ADDITION FOR NEW FAMILY ROOM, KITCHEN, LAUNDRY. 2ND FLOOR ADDITION FOR NEW MASTER SUITE & STAIRS. (1 OF 3)
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | VU NGUYEN |
| Green Plans Picked Up | 10/24/2019 | APPLICANT |
| Corrections Issued | 11/5/2019 | VU NGUYEN |
| Quality Review Completed | 11/20/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/25/2019 | APPLICANT |
| Applicant returned to address corrections | 1/8/2020 | VU NGUYEN |
| Plan Check Approved | 1/10/2020 | VU NGUYEN |
| Issued | 2/14/2020 | LADBS |
| CofO in Progress | 2/4/2022 | JUAN VALENZUELA |
| No Progress | 4/15/2022 | KENNETH NAGLE |
| CofO in Progress | 5/13/2022 | KENNETH NAGLE |
| Permit Finaled | 5/16/2022 | DANIEL ORRANTE |
| CofO Issued | 5/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/5/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 12/5/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 12/5/2019 | ELAINE LEI |
| CPC | Cleared | 12/5/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | ELAINE LEI |
| Sewer availability | Cleared | 12/5/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 12/18/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/18/2019 | THOMAS LANG |
| Green Code | Cleared | 12/19/2019 | COLIN LOREDO |
| GPI Written Notices | Cleared | 1/8/2020 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 1/8/2020 | VU NGUYEN |
| Address approval | Cleared | 1/30/2020 | ELAINE LEI |
Contact Information
| Architect | Beltran,, Xavier A; Lic. No.: C34473 | 3012 FANITA STREET LOS ANGELES, CA 90026 |
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | 11661 SAN VICENTE BLVD STE 302 LOS ANGELES, CA 90049 |
| Engineer | Shah,, Kamal Rajendra; Lic. No.: C46200 | 28039 SMYTH DR STE 200 VALENCIA, CA 91355 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/21/2020 | Partial Inspection | KENNETH NAGLE |
| Pre-Inspection | 4/24/2020 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 5/21/2020 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 5/26/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/8/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/10/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 8/6/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 8/10/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 8/20/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Steel/Welding | 9/8/2020 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 9/21/2020 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 9/21/2020 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 10/5/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 10/9/2020 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 10/20/2020 | Approved | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Steel/Welding | 11/16/2020 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 11/30/2020 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 12/3/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2020 | Conditional Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/15/2020 | Partial Approval | MATT KELLERMAN |
| HVAC-Rough | 12/15/2020 | Partial Approval | MATT KELLERMAN |
| HVAC-Rough | 12/24/2020 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 1/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Steel/Welding | 1/8/2021 | Corrections Issued | ROBERT SHELLY |
| ELECTRICAL-Rough | 1/12/2021 | Partial Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/27/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 1/27/2021 | Partial Approval | JOHN KIDWELL |
| Insulation | 2/3/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 2/4/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/17/2021 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 2/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 2/25/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/9/2021 | Partial Approval | PIERRE VEGA |
| Interior/Exterior Lathing | 4/14/2021 | Not Ready for Inspection | PIERRE VEGA |
| Interior/Exterior Lathing | 4/28/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 4/30/2021 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 5/6/2021 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 5/27/2021 | Partial Approval | JUAN VALENZUELA |
| Service/Power Release | 7/13/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 9/8/2021 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/23/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 9/24/2021 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Final | 9/27/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/20/2021 | Approved | JUAN VALENZUELA |
| Final | 10/20/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/20/2021 | Approved | JUAN VALENZUELA |
| Green Building Final | 10/20/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 10/20/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 10/27/2021 | Approved | ANDREW NAVE |
| Final | 10/27/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 10/27/2021 | Not Ready for Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Approved | ANDREW NAVE |
| Final | 2/4/2022 | OK to Issue CofO | JUAN VALENZUELA |