173 N CARMELINA AVE 90049

Certificate Information: 173 N CARMELINA AVE 90049

Application / Permit
19014-10000-05555
Plan Check / Job No.
B19LA21619
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SINGLE FAMILY RESIDENCE ADDITION & REMODEL. GROUND FLOOR ADDITION FOR NEW FAMILY ROOM, KITCHEN, LAUNDRY. 2ND FLOOR ADDITION FOR NEW MASTER SUITE & STAIRS. (1 OF 3)
Permit Issued
Issued on 2/14/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 VU NGUYEN
Green Plans Picked Up 10/24/2019 APPLICANT
Corrections Issued 11/5/2019 VU NGUYEN
Quality Review Completed 11/20/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/25/2019 APPLICANT
Applicant returned to address corrections 1/8/2020 VU NGUYEN
Plan Check Approved 1/10/2020 VU NGUYEN
Issued 2/14/2020 LADBS
CofO in Progress 2/4/2022 JUAN VALENZUELA
No Progress 4/15/2022 KENNETH NAGLE
CofO in Progress 5/13/2022 KENNETH NAGLE
Permit Finaled 5/16/2022 DANIEL ORRANTE
CofO Issued 5/16/2022 DANIEL ORRANTE
Permit Finaled 5/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/5/2019 ELAINE LEI
BHO/Hillside ordinance Cleared 12/5/2019 ELAINE LEI
BHO/Hillside ordinance Cleared 12/5/2019 ELAINE LEI
CPC Cleared 12/5/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 12/5/2019 ELAINE LEI
Sewer availability Cleared 12/5/2019 ELAINE LEI
Low Impact Development Cleared 12/18/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/18/2019 THOMAS LANG
Green Code Cleared 12/19/2019 COLIN LOREDO
GPI Written Notices Cleared 1/8/2020 VU NGUYEN
Grading Pre-Inspection Cleared 1/8/2020 VU NGUYEN
Address approval Cleared 1/30/2020 ELAINE LEI

Contact Information

Architect Beltran,, Xavier A; Lic. No.: C34473 3012 FANITA STREET      LOS ANGELES, CA 90026
Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049
Engineer Shah,, Kamal Rajendra; Lic. No.: C46200 28039 SMYTH DR STE 200      VALENCIA, CA 91355
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/21/2020 Partial Inspection KENNETH NAGLE
Pre-Inspection 4/24/2020 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 5/21/2020 Partial Approval TIM CHRISTENSEN
Underground Mechanical 5/26/2020 Not Ready for Inspection TIM CHRISTENSEN
Footing/Foundation/Slab 7/8/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 7/10/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 8/6/2020 Not Ready for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 8/10/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 8/20/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 8/31/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval TIM CHRISTENSEN
Deputy Steel/Welding 9/8/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 9/21/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 9/21/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/22/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/5/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/8/2020 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 10/9/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 10/20/2020 Approved TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/22/2020 Partial Approval TIM CHRISTENSEN
Deputy Steel/Welding 11/16/2020 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 11/30/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 12/3/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Conditional Approval JOHN KIDWELL
ELECTRICAL-Rough 12/15/2020 Partial Approval MATT KELLERMAN
HVAC-Rough 12/15/2020 Partial Approval MATT KELLERMAN
HVAC-Rough 12/24/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 1/7/2021 Not Ready for Inspection JOHN KIDWELL
Deputy Steel/Welding 1/8/2021 Corrections Issued ROBERT SHELLY
ELECTRICAL-Rough 1/12/2021 Partial Inspection ANDREW NAVE
BUILDING-Rough-Frame 1/27/2021 Partial Approval JOHN KIDWELL
Green Building Rough 1/27/2021 Partial Approval JOHN KIDWELL
Insulation 2/3/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 2/4/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/17/2021 Partial Approval JUAN VALENZUELA
Drywall Nailing 2/19/2021 Not Ready for Inspection JUAN VALENZUELA
Drywall Nailing 2/25/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/9/2021 Partial Approval PIERRE VEGA
Interior/Exterior Lathing 4/14/2021 Not Ready for Inspection PIERRE VEGA
Interior/Exterior Lathing 4/28/2021 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 4/30/2021 Partial Approval JUAN VALENZUELA
Underground Mechanical 5/6/2021 Partial Approval JUAN VALENZUELA
Underground Mechanical 5/27/2021 Partial Approval JUAN VALENZUELA
Service/Power Release 7/13/2021 Not Ready for Inspection JUAN VALENZUELA
Gas Test 9/8/2021 Approved JESUS RODRIGUEZ
PLUMBING-Final 9/23/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 9/24/2021 Corrections Issued JUAN VALENZUELA
HVAC-Final 9/27/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/20/2021 Approved JUAN VALENZUELA
Final 10/20/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 10/20/2021 Approved JUAN VALENZUELA
Green Building Final 10/20/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 10/20/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/27/2021 Approved ANDREW NAVE
Final 10/27/2021 Corrections Issued ANDREW NAVE
HVAC-Final 10/27/2021 Not Ready for Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/27/2021 SGSOV Approved ANDREW NAVE
Final 2/4/2022 OK to Issue CofO JUAN VALENZUELA