8048 W FENWICK ST 91040
Certificate Information: 8048 W FENWICK ST 91040
- Application / Permit
- 19014-10000-05535
- Plan Check / Job No.
- B19LA21556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-5" X 26' DETACHED GARAGE TO ACCESSORY DWELLING UNIT W/ NEW 16'-9" X 18'-9" 2ND FLOOR ADDITION PER AB494 AND SB229.
- Permit Issued
- Issued on 4/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 11/19/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 12/4/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 1/13/2020 | APPLICANT |
| Green Plans Picked Up | 1/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/25/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 3/11/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 3/27/2020 | CHUNG-WEN CHUANG |
| Issued | 4/3/2020 | LADBS |
| CofO in Progress | 4/11/2023 | WILLIAM WREN |
| Permit Finaled | 4/14/2023 | MICHAEL SMITH |
| CofO Issued | 4/14/2023 | MICHAEL SMITH |
| Permit Finaled | 4/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 1/13/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/23/2020 | THOMAS LANG |
| Address approval | Cleared | 2/5/2020 | JUAN ASHTON |
| Green Code | Cleared | 2/10/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 2/11/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/24/2021 | Partial Approval | MATTHEW NELSON |
| Sewer | 2/24/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 4/13/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/15/2021 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/15/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/15/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/15/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/23/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/7/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/7/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 5/7/2021 | Approved | MATTHEW NELSON |
| Insulation | 6/1/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 6/1/2021 | Approved | DEANDRE HOFFMAN |
| Insulation | 6/11/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 2/3/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 6/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/26/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 9/26/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/26/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 10/5/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 10/17/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 10/17/2022 | Approved | MATTHEW NELSON |
| Final | 1/17/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 1/17/2023 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Not Ready | WILLIAM WREN |
| Smoke Detectors | 1/17/2023 | Approved | WILLIAM WREN |
| Final | 2/7/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Final | 2/10/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 2/10/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | WILLIAM WREN |
| Final | 3/17/2023 | Corrections Issued | WILLIAM WREN |
| Final | 4/3/2023 | Corrections Issued | WILLIAM WREN |
| Final | 4/10/2023 | OK to Issue CofO | WILLIAM WREN |