1820 N REDESDALE AVE 90026
Certificate Information: 1820 N REDESDALE AVE 90026
- Application / Permit
- 19014-10000-05470
- Plan Check / Job No.
- B19LA21302
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PARTIAL DEMOLITION AND RENOVATION OF EXISTING SINGLE FAMILY RESIDENCE AND NEW TWO STORY ADDITION WITH WALK OUT TERRACES AT MAIN LEVEL AND LOWER LEVEL
- Permit Issued
- Issued on 5/8/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | MIGUEL JIMENEZ |
| Corrections Issued | 11/1/2019 | MIGUEL JIMENEZ |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Quality Review Completed | 11/7/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 11/15/2019 | MIGUEL JIMENEZ |
| Applicant returned to address corrections | 12/12/2019 | MIGUEL JIMENEZ |
| Applicant returned to address corrections | 1/16/2020 | MIGUEL JIMENEZ |
| Plan Check Approved | 2/5/2020 | MIGUEL JIMENEZ |
| Issued | 5/8/2020 | LADBS |
| CofO in Progress | 7/19/2023 | THOMAS LOGRASSO |
| Permit Finaled | 7/25/2023 | DEROLD HAUFF |
| CofO Issued | 7/25/2023 | DEROLD HAUFF |
| Permit Finaled | 7/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 12/16/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 12/16/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 12/16/2019 | EMIL KYUPELYAN |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | ELAINE LEI |
| Grading Pre-Inspection | Cleared | 1/29/2020 | PATRICK MISCHLICH |
Contact Information
| Architect | Ferrier,, G Graham; Lic. No.: C32942 | FERRIER ARCHITECTURE STUDIO 1820 REDESDALE AVE. LOS ANGELES, CA 90026 |
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/21/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/5/2020 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 6/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 6/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/8/2020 | Approved | ENRIQUE MIRELES |
| Sewer | 7/8/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/17/2020 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 7/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/5/2020 | Off-Hour Fees Due | |
| PLUMBING-Rough | 8/5/2020 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 8/7/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/7/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/11/2020 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 8/11/2020 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/23/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/9/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/9/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 11/9/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/9/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/18/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/18/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/18/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/18/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/18/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/1/2020 | Approved | ROBERT VORHIS |
| Gas Test | 12/1/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 12/1/2020 | Partial Approval | ROBERT VORHIS |
| Shower Pan | 12/22/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 3/10/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 3/10/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 3/10/2021 | Corrections Issued | SCOTT FINNILA |
| Service/Power Release | 3/10/2021 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 3/10/2021 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 3/15/2021 | Not Ready for Inspection | SCOTT FINNILA |
| HVAC-Final | 3/15/2021 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Final | 3/15/2021 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 11/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Final | 11/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/18/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 11/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 11/18/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 11/18/2022 | Approved | THOMAS LOGRASSO |
| Final | 6/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 7/13/2023 | No Access for Inspection | THOMAS LOGRASSO |
| Final | 7/18/2023 | OK to Issue CofO | THOMAS LOGRASSO |