1243 W 60TH PL 90044

Certificate Information: 1243 W 60TH PL 90044

Application / Permit
19014-10000-05445
Plan Check / Job No.
B19LA21184
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD NEW ADU 650 SQ FT TO (E) HOME 1,559 SQ/FT TO BE REDUCED 150 SQ/FT FOR NEW ADU BEDROOM. NEW SQ/FT FOR (E) HOME 1409 SQ/FT.
Permit Issued
Issued on 2/13/2020
Issuing Office
South Los Angeles
Current Status
CofO Corrected on 9/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 JESSE VIDUYA
Corrections Issued 10/31/2019 JESSE VIDUYA
Quality Review Completed 11/7/2019 JOSE RODRIGUEZ
Green Plans Picked Up 11/19/2019 APPLICANT
Building Plans Picked Up 12/5/2019 APPLICANT
Plan Check Approved 2/4/2020 JESSE VIDUYA
Issued 2/13/2020 LADBS
CofO in Progress 8/18/2020 COREY HUPP
CofO Issued-Status Void 9/27/2020 DEROLD HAUFF
Permit Finaled-Status Void 9/27/2020 DEROLD HAUFF
Re-Activate Permit 9/29/2020 DEROLD HAUFF
Permit Finaled 9/29/2020 DEROLD HAUFF
CofO Corrected 9/29/2020 DEROLD HAUFF
Permit Finaled 9/29/2020 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/31/2019 VIVIAN LAO
Address approval Cleared 1/22/2020 CELINA MORENO
Hydrant and Access approval Cleared 1/22/2020 GILBERT URREA
Low Impact Development Cleared 1/22/2020 ORVAL HERNANDEZ-MARCIAL
Eng Process Fee Ord 176,300 Cleared 2/3/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 2/3/2020 EMIL KYUPELYAN
Sewer availability Cleared 2/3/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 3/12/2020 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 5/5/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Approved FREDDIE RIVERA
Green Building Rough 5/5/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 5/5/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/26/2020 Approved FREDDIE RIVERA
Green Building Rough 5/26/2020 Approved FREDDIE RIVERA
Insulation 5/26/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/26/2020 Partial Approval FREDDIE RIVERA
Drywall Nailing 6/3/2020 Approved SABAS ALONSO
Final 6/3/2020 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 6/3/2020 Approved SABAS ALONSO
Shower Pan 6/3/2020 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/9/2020 SGSOV Not Ready FREDDIE RIVERA
Final 8/11/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 8/11/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 8/11/2020 Approved FREDDIE RIVERA
Final 8/17/2020 OK to Issue CofO COREY HUPP
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Approved COREY HUPP
Service/Power Release 9/14/2020 Corrections Issued FREDDIE RIVERA
Service/Power Release 9/18/2020 Approved COREY HUPP