3775 S SUTRO AVE 90018

Certificate Information: 3775 S SUTRO AVE 90018

Application / Permit
19014-10000-05382
Plan Check / Job No.
B19LA20915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1) I-STORY ADDITION 26'-2½" x 17'-2" TO AN EXISTING SINGLE FAMILY DWELLING , INTERIOR REMODEL TO REMODEL KITCHENAND CHANGE FLOOR LAYOUT, AND EXTERIOR ALTERATIONS TO CHANGE WINDOWS
Permit Issued
Issued on 2/12/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/28/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 MINA HABIB
Corrections Issued 11/25/2019 MINA HABIB
Quality Review Completed 12/17/2019 KESETE HAREGOT
Building Plans Picked Up 12/19/2019 APPLICANT
Applicant returned to address corrections 1/15/2020 MINA HABIB
Applicant returned to address corrections 1/28/2020 MINA HABIB
Plan Check Approved 2/10/2020 MINA HABIB
Issued 2/12/2020 LADBS
Green Plans Picked Up 4/24/2020 APPLICANT
CofO in Progress 10/22/2020 DONALD CRICHLOW
Permit Finaled 10/28/2020 DEROLD HAUFF
CofO Issued 10/28/2020 DEROLD HAUFF
Permit Finaled 10/28/2020 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/14/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/15/2020 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 1/16/2020 MINA HABIB
Eng Process Fee Ord 176,300 Cleared 2/5/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 2/5/2020 CELINA MORENO

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Chen,, Emily Hsiao Han; Lic. No.: C73319 22629 LAKESIDE LN      LAKE FOREST, CA 926303035

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2020 Approved COREY HUPP
BUILDING-Rough-Frame 3/4/2020 Partial Approval COREY HUPP
Green Building Rough 3/4/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/4/2020 Partial Approval COREY HUPP
Underground Mechanical 3/4/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 4/27/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 4/27/2020 Approved ROBERT MCDOWELL
Green Building Rough 4/27/2020 Approved ROBERT MCDOWELL
HVAC-Rough 4/27/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 4/27/2020 Approved ROBERT MCDOWELL
Sewer 4/27/2020 Approved ROBERT MCDOWELL
Insulation 5/1/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/1/2020 Approved SABAS ALONSO
Shower Pan 5/5/2020 Approved SABAS ALONSO
Drywall Nailing 5/8/2020 Approved SABAS ALONSO
Final 8/17/2020 Not Ready for Inspection COREY HUPP
Green Building Final 8/17/2020 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Not Ready COREY HUPP
Smoke Detectors 8/17/2020 Not Ready for Inspection COREY HUPP
Final 10/15/2020 Corrections Issued DONALD CRICHLOW
Green Building Final 10/15/2020 Corrections Issued DONALD CRICHLOW
HVAC-Final 10/15/2020 Corrections Issued DONALD CRICHLOW
PLUMBING-Final 10/15/2020 Approved DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved DONALD CRICHLOW
Smoke Detectors 10/15/2020 Approved DONALD CRICHLOW
ELECTRICAL-Final 10/22/2020 Approved DONALD CRICHLOW
Final 10/22/2020 OK to Issue CofO DONALD CRICHLOW
Green Building Final 10/22/2020 Approved DONALD CRICHLOW
HVAC-Final 10/22/2020 Approved DONALD CRICHLOW
Interior/Exterior Lathing 10/22/2020 Approved DONALD CRICHLOW