6344 W FOUNTAIN AVE 90028

Certificate Information: 6344 W FOUNTAIN AVE 90028

Application / Permit
19014-10000-05376
Plan Check / Job No.
B19LA20905
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ALTERATION AND ADDITION TO AN EXISTING 2-STORY OFFICE BUILDING OVER TWO LEVELS OF SUBTERRANEAN GARAGE.
Permit Issued
Issued on 9/28/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 JOHNNY WU
Corrections Issued 11/6/2019 JOHNNY WU
Disabled Access Plans Picked Up 11/21/2019 APPLICANT
Quality Review Completed 11/22/2019 JOSE RODRIGUEZ
Applicant returned to address corrections 2/3/2020 JOHNNY WU
Applicant returned to address corrections 2/20/2020 JOHNNY WU
Applicant returned to address corrections 2/27/2020 JOHNNY WU
Applicant returned to address corrections 3/12/2020 JOHNNY WU
Applicant returned to address corrections 4/14/2020 JOHNNY WU
Applicant returned to address corrections 4/15/2020 JOHNNY WU
Applicant returned to address corrections 4/16/2020 JOHNNY WU
Applicant returned to address corrections 4/16/2020 JOHNNY WU
Applicant returned to address corrections 5/1/2020 JOHNNY WU
Applicant returned to address corrections 8/14/2020 JOHNNY WU
Applicant returned to address corrections 2/3/2021 JOHNNY WU
Green Plans Picked Up 2/23/2021 APPLICANT
Applicant returned to address corrections 3/1/2021 JOHNNY WU
Applicant returned to address corrections 3/26/2021 JOHNNY WU
Applicant returned to address corrections 6/24/2021 JOHNNY WU
Applicant returned to address corrections 8/25/2021 JOHNNY WU
Applicant returned to address corrections 8/27/2021 JOHNNY WU
Applicant returned to address corrections 9/8/2021 JOHNNY WU
Plan Check Approved 9/8/2021 JOHNNY WU
Issued 9/28/2021 APPLICANT
Building Plans Picked Up 9/30/2021 APPLICANT
CofO in Progress 7/16/2024 TIMOTHY POWELL
CofO in Progress 7/19/2024 TIMOTHY POWELL
CofO in Progress 7/19/2024 TIMOTHY POWELL
Permit Finaled 8/7/2024 ERNESTO CORRAL
CofO Issued 8/7/2024 ERNESTO CORRAL
Permit Finaled 8/7/2024 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 1/10/2020 ELAINE LEI
ZA Case Cleared 1/10/2020 RICHARD REASER
ZA Case Cleared 1/10/2020 RICHARD REASER
ZA Case Cleared 1/10/2020 RICHARD REASER
ZI Cleared 1/10/2020 RICHARD REASER
Address approval Cleared 1/15/2020 EMIL KYUPELYAN
Green Code Cleared 2/13/2020 COLIN LOREDO
Construction near power lines Cleared 4/9/2020 RIDWAN HARDY
Construction within easement Cleared 4/9/2020 RIDWAN HARDY
Bicycle Parking Cleared 6/10/2020 ELENA LOPEZ
Low Impact Development Cleared 12/8/2020 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/9/2020 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 12/21/2020 RENZ SORIANO
Sewer availability Cleared 12/21/2020 RENZ SORIANO
Building over 3-story or 36-ft Cleared 2/3/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 2/3/2021 CALOSHA APPROVED
DAS Clearance Cleared 4/22/2021 JOHNNY WU
Project located in CRA area Cleared 5/27/2021 GISELLE CORELLA
ZI Cleared 5/27/2021 GISELLE CORELLA
ZI Cleared 5/27/2021 GISELLE CORELLA
Driveway location Cleared 6/7/2021 TAIMOUR TANAVOLI
Internal circulation Cleared 6/7/2021 TAIMOUR TANAVOLI
Encroachment in public way Cleared 6/15/2021 JEREMY CHOK
Highway dedication Cleared 6/15/2021 RENZ SORIANO
Transportation Demand Ord. Cleared 7/1/2021 TAIMOUR TANAVOLI
Hydrant and Access approval Cleared 7/13/2021 KURT CORRAL
Miscellaneous Cleared 8/6/2021 TANAT SATIDKIT
Mechanical Car Lift Cleared 8/19/2021 DOMINIQUE MEDINA
Comm Cor/Mini-Mall Cleared 8/20/2021 MARITZA PRZEKOP

Contact Information

Architect House,, James Douglas; Lic. No.: C15526 10125 WASHINGTON BLVD      CULVER CITY, CA 90232
Contractor Del Amo Construction Inc; Lic. No.: 744458-B 23840 MADISON STREET      TORRANCE, CA 90505
Engineer Davis,, Richard Hays; Lic. No.: C48082 2015 CANTATA DR      LOS ANGELES, CA 90068
Engineer Mcdermott,, Thomas Patrick; Lic. No.: L8555 2016 E GLENOAKS BLVD      GLENDALE, CA 91206
Engineer Prince,, Scott Taylor; Lic. No.: C83961 1720 BUTLER AVE 3      LOS ANGELES, CA 90025
Engineer Scott,, Charles Lawrence; Lic. No.: L8742 29716 BENCHMARK COURT      ESCONDIDO, CA 92026
Engineer Smith,, Chris Wayne; Lic. No.: S6106 35 CATAMARAN ST      MARINA DEL REY, CA 90292
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505
Landscape Architect Compton,, Allen Ayres; Lic. No.: LA5565 423 GIN LING WAY      LOS ANGELES, CA 90012

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2021 Partial Inspection SORIN CIRSTOIU
Pre-Inspection 10/29/2021 Partial Approval SORIN CIRSTOIU
Pre-Inspection 11/8/2021 Partial Approval SORIN CIRSTOIU
Piling/Pier/Caisson 11/12/2021 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 11/15/2021 Partial Inspection SORIN CIRSTOIU
Piling/Pier/Caisson 12/7/2021 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 12/20/2021 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 12/20/2021 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 12/21/2021 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 12/21/2021 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 1/11/2022 Conditional Approval JONATHAN QUACH
Reinforced Concrete Frame 1/11/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 1/12/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 1/12/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 1/13/2022 Approved SORIN CIRSTOIU
Green Building Rough 1/13/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 1/13/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 1/14/2022 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 1/14/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 1/18/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 1/18/2022 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 1/18/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Masonry 1/19/2022 Conditional Approval JONATHAN QUACH
Green Building Rough 1/19/2022 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 1/19/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/20/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/21/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/24/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/25/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/26/2022 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 1/26/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/27/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/27/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 1/28/2022 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 1/28/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 2/1/2022 Approved SORIN CIRSTOIU
Green Building Rough 2/1/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 2/1/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 2/2/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 2/3/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 2/4/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 2/7/2022 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 2/7/2022 Partial Approval SORIN CIRSTOIU
Green Building Rough 2/15/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 2/15/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 2/16/2022 Partial Approval SORIN CIRSTOIU
Green Building Rough 2/18/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 2/18/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 2/25/2022 Partial Approval SORIN CIRSTOIU
Green Building Rough 3/1/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 3/1/2022 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 3/18/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 4/6/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 4/12/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 4/14/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 4/25/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 4/26/2022 Conditional Approval JONATHAN QUACH
Reinforced Concrete Frame 5/10/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 5/13/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 5/20/2022 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 5/24/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 6/7/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 6/13/2022 Partial Approval MARK FERRARI
Green Building Rough 6/16/2022 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 6/16/2022 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 6/22/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 6/25/2022 Partial Approval BRUCE CAMPBELL
Reinforced Concrete Frame 6/27/2022 Approved JONATHAN QUACH
Light Gage Steel Frame 7/1/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 7/6/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 7/11/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 7/13/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 7/19/2022 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/22/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 7/25/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 7/26/2022 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/27/2022 Conditional Approval WINSTON DUNNING
Green Building Rough 7/27/2022 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 7/27/2022 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/29/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/2/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/4/2022 Conditional Approval WINSTON DUNNING
Green Building Rough 8/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 8/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/8/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 8/8/2022 Conditional Approval DARRYL ARNOLD
Reinforced Masonry Frame 8/8/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Masonry 8/10/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/11/2022 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 8/11/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Masonry 8/12/2022 Conditional Approval RUSSELL BONVOULOIR
Reinforced Concrete Frame 8/12/2022 Partial Approval RUSSELL BONVOULOIR
Reinforced Concrete Frame 8/13/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 8/19/2022 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 8/19/2022 Partial Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 8/24/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 8/26/2022 Conditional Approval WINSTON DUNNING
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Partial Approval TED RIES
Deputy Steel/Welding 8/31/2022 Conditional Approval WINSTON DUNNING
Deputy Wood Construction 8/31/2022 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 9/1/2022 Conditional Approval WINSTON DUNNING
Deputy Wood Construction 9/1/2022 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 9/1/2022 Partial Approval TIMOTHY BUXTON
Deputy Wood Construction 9/2/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 9/8/2022 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/8/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 9/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/22/2022 Partial Approval JONATHAN QUACH
Deputy Steel/Welding 9/28/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/6/2022 Approved JONATHAN QUACH
Reinforced Concrete Frame 10/6/2022 Partial Approval JONATHAN QUACH
Green Building Rough 10/10/2022 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 10/10/2022 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 10/14/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 10/14/2022 Not Ready for Inspection DAVID BURKHEAD
Wall Anchors 10/14/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Steel/Welding 10/17/2022 Conditional Approval JONATHAN QUACH
Light Gage Steel Frame 10/25/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 10/25/2022 Partial Inspection JONATHAN QUACH
Masonry Wall/Backfill 11/1/2022 Approved DARRYL ARNOLD
Green Building Rough 11/3/2022 Not Ready for Inspection JONATHAN QUACH
Light Gage Steel Frame 11/3/2022 Partial Approval JONATHAN QUACH
Masonry Wall/Backfill 11/3/2022 Partial Approval JONATHAN QUACH
Reinforced Masonry Frame 11/3/2022 Partial Approval JONATHAN QUACH
Green Building Rough 11/15/2022 Partial Inspection GREGORY POMISH
Reinforced Masonry Frame 11/15/2022 Partial Approval GREGORY POMISH
Wall Anchors 11/16/2022 Partial Approval ALFREDO LOPEZ
Masonry Wall/Backfill 11/17/2022 Partial Inspection RUSSELL BONVOULOIR
Reinforced Concrete Frame 11/17/2022 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 11/30/2022 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 11/30/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 12/20/2022 Partial Approval VAHE KELEDJIAN
Light Gage Steel Frame 12/27/2022 Partial Inspection RONALD JIMENEZ
Structural Steel Frame 12/27/2022 Corrections Issued RONALD JIMENEZ
Interior/Exterior Lathing 12/28/2022 Partial Approval RONALD JIMENEZ
Insulation 1/4/2023 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 1/9/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 1/9/2023 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 1/17/2023 Partial Inspection RONALD JIMENEZ
Interior/Exterior Lathing 1/19/2023 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 1/27/2023 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 2/10/2023 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 2/23/2023 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 3/13/2023 Partial Approval RONALD JIMENEZ
Structural Steel Frame 3/13/2023 Corrections Issued RONALD JIMENEZ
Deputy Steel/Welding 3/17/2023 Conditional Approval TIMOTHY POWELL
Interior/Exterior Lathing 3/17/2023 Partial Approval RAFAEL CORTES
Deputy Steel/Welding 3/21/2023 Conditional Approval RONALD JIMENEZ
Light Gage Steel Frame 3/21/2023 Partial Inspection RONALD JIMENEZ
Deputy Steel/Welding 3/22/2023 Conditional Approval RONALD JIMENEZ
Special/Order Compliance 8/22/2023 Approved RONALD JIMENEZ
Special/Order Compliance 8/30/2023 Approved RONALD JIMENEZ
Special/Order Compliance 11/28/2023 Approved RONALD JIMENEZ
Pre-Inspection 2/22/2024 No Access for Inspection RAFAEL CORTES
Final 3/6/2024 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 3/6/2024 Approved RAFAEL CORTES
Green Building Final 3/6/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 3/6/2024 Approved RAFAEL CORTES
Reinforced Masonry Frame 3/6/2024 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 3/6/2024 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 3/6/2024 Approved RAFAEL CORTES
Final 5/23/2024 Partial Inspection TIMOTHY POWELL
Green Building Final 5/23/2024 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Not Ready TIMOTHY POWELL
Final 5/29/2024 Partial Inspection TIMOTHY POWELL
Green Building Final 5/29/2024 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Not Ready TIMOTHY POWELL
Final 6/18/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Final 6/18/2024 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready RAFAEL CORTES
Final 6/20/2024 Partial Inspection TIMOTHY POWELL
Pre-Inspection 6/20/2024 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV No Gas TIMOTHY POWELL
Special/Order Compliance 6/27/2024 Corrections Issued TIMOTHY POWELL
Final 7/16/2024 OK to Issue CofO TIMOTHY POWELL