442-442 1/2 E 105TH ST 90003
Certificate Information: 442-442 1/2 E 105TH ST 90003
- Application / Permit
- 19014-10000-05364
- Plan Check / Job No.
- B19LA20838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING PER AB 494 AND SB 229 WITH ADDITION TO THE SIDES ( 3'-5" X 17'-10" & 4'-11" X 17'-10")
- Permit Issued
- Issued on 10/17/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 10/8/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 10/15/2019 | MICHAEL LOPEZ |
| Plan Check Approved | 10/17/2019 | KEVIN MORALES |
| Issued | 10/17/2019 | LADBS |
| CofO in Progress | 4/6/2021 | EUGENE CASSIDY |
| Permit Finaled | 4/24/2021 | DEROLD HAUFF |
| CofO Issued | 4/24/2021 | DEROLD HAUFF |
| Permit Finaled | 4/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 10/15/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/17/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/10/2019 | Conditional Approval | WILLIAM ROSE |
| Footing/Foundation/Slab | 12/12/2019 | Corrections Issued | WILLIAM ROSE |
| PLUMBING-Rough | 12/12/2019 | Partial Approval | WILLIAM ROSE |
| Footing/Foundation/Slab | 12/19/2019 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 12/19/2019 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/2/2020 | Approved | WILLIAM ROSE |
| PLUMBING-Final | 1/2/2020 | Corrections Issued | WILLIAM ROSE |
| BUILDING-Rough-Frame | 1/9/2020 | Corrections Issued | WILLIAM ROSE |
| Green Building Rough | 1/9/2020 | Not Ready for Inspection | WILLIAM ROSE |
| PLUMBING-Rough | 1/9/2020 | Partial Approval | WILLIAM ROSE |
| BUILDING-Rough-Frame | 2/7/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 2/7/2020 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 4/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/17/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/17/2020 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 4/23/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 4/28/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/28/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/28/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/6/2020 | Conditional Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Approved | BRIAN CHRISTIAN |
| Insulation | 5/6/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 5/19/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 5/19/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 8/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/31/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 8/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/31/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 8/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/21/2020 | Approved | EUGENE CASSIDY |
| Final | 10/21/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/21/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/21/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/21/2020 | Approved | EUGENE CASSIDY |
| Final | 12/8/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/10/2021 | Approved | EUGENE CASSIDY |
| Final | 3/10/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 3/10/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/10/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/16/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/26/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 4/6/2021 | OK to Issue CofO | EUGENE CASSIDY |