442-442 1/2 E 105TH ST 90003

Certificate Information: 442-442 1/2 E 105TH ST 90003

Application / Permit
19014-10000-05364
Plan Check / Job No.
B19LA20838
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING PER AB 494 AND SB 229 WITH ADDITION TO THE SIDES ( 3'-5" X 17'-10" & 4'-11" X 17'-10")
Permit Issued
Issued on 10/17/2019
Issuing Office
Metro
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2019 APPLICANT
Assigned to Plan Check Engineer 10/8/2019 FARSHAD ALIMOHAMADI
Corrections Issued 10/8/2019 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/15/2019 MICHAEL LOPEZ
Plan Check Approved 10/17/2019 KEVIN MORALES
Issued 10/17/2019 LADBS
CofO in Progress 4/6/2021 EUGENE CASSIDY
Permit Finaled 4/24/2021 DEROLD HAUFF
CofO Issued 4/24/2021 DEROLD HAUFF
Permit Finaled 4/24/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/15/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 10/15/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/17/2019 ERIK BEASLEY
Sewer availability Cleared 10/17/2019 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/10/2019 Conditional Approval WILLIAM ROSE
Footing/Foundation/Slab 12/12/2019 Corrections Issued WILLIAM ROSE
PLUMBING-Rough 12/12/2019 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 12/19/2019 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 12/19/2019 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/2/2020 Approved WILLIAM ROSE
PLUMBING-Final 1/2/2020 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 1/9/2020 Corrections Issued WILLIAM ROSE
Green Building Rough 1/9/2020 Not Ready for Inspection WILLIAM ROSE
PLUMBING-Rough 1/9/2020 Partial Approval WILLIAM ROSE
BUILDING-Rough-Frame 2/7/2020 Corrections Issued JOHN KLARIN
Green Building Rough 2/7/2020 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 4/17/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/17/2020 Approved EUGENE CASSIDY
Wood Frame 4/17/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 4/23/2020 Partial Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 4/28/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/28/2020 Approved EUGENE CASSIDY
PLUMBING-Final 4/28/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/6/2020 Conditional Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Approved BRIAN CHRISTIAN
Insulation 5/6/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/19/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/19/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 8/31/2020 Not Ready for Inspection EUGENE CASSIDY
Final 8/31/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 8/31/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/31/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 8/31/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/21/2020 Approved EUGENE CASSIDY
Final 10/21/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 10/21/2020 Approved EUGENE CASSIDY
Green Building Rough 10/21/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 10/21/2020 Approved EUGENE CASSIDY
Final 12/8/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 3/10/2021 Approved EUGENE CASSIDY
Final 3/10/2021 Corrections Issued EUGENE CASSIDY
HVAC-Final 3/10/2021 Approved EUGENE CASSIDY
PLUMBING-Final 3/10/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved EUGENE CASSIDY
ELECTRICAL-Final 3/16/2021 Corrections Issued EUGENE CASSIDY
Final 3/26/2021 Corrections Issued EUGENE CASSIDY
Final 4/6/2021 OK to Issue CofO EUGENE CASSIDY