6425 N AGNES AVE 91606

Certificate Information: 6425 N AGNES AVE 91606

Application / Permit
19014-10000-05342
Plan Check / Job No.
B19LA20741
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 15'-6" X 32'-3" 1-STORY ADU ATTACHED TO (E) 18'-8" X 20' 1-STORY 2-CAR DETACHED GARAGE.
Permit Issued
Issued on 3/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 CHUNG-WEN CHUANG
Green Plans Picked Up 10/16/2019 APPLICANT
Corrections Issued 11/7/2019 CHUNG-WEN CHUANG
Quality Review Completed 11/21/2019 KESETE HAREGOT
Building Plans Picked Up 11/25/2019 APPLICANT
Applicant returned to address corrections 3/10/2020 CHUNG-WEN CHUANG
Plan Check Approved 3/11/2020 CHUNG-WEN CHUANG
Issued 3/16/2020 LADBS
CofO in Progress 1/22/2021 DANIEL DREW
CofO Issued 8/24/2022 DANIEL ORRANTE
Permit Finaled 8/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/4/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/4/2019 ELENA LOPEZ
Sewer availability Cleared 12/4/2019 ELENA LOPEZ
Green Code Cleared 12/26/2019 KHEDER ALRAZAA
Low Impact Development Cleared 1/14/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/14/2020 JEANIE LAM
Construction near power lines Cleared 2/10/2020 RIDWAN HARDY
Construction within easement Cleared 2/10/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/22/2020 Corrections Issued BEAU COLLINS
Insulation 5/6/2020 No Access for Inspection RAYMOND KEHOE
Footing/Foundation/Slab 6/11/2020 Corrections Issued DANIEL DREW
Footing/Foundation/Slab 6/16/2020 Approved RAYMOND KEHOE
Wood Frame 8/4/2020 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 8/14/2020 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 8/14/2020 Corrections Issued DANIEL DREW
Green Building Rough 8/14/2020 Not Ready for Inspection DANIEL DREW
Insulation 8/14/2020 Partial Approval DANIEL DREW
PLUMBING-Rough 8/14/2020 Corrections Issued DANIEL DREW
ELECTRICAL-Rough 8/28/2020 Approved DANIEL DREW
HVAC-Rough 8/28/2020 Approved DANIEL DREW
PLUMBING-Rough 8/28/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 9/2/2020 Approved DANIEL DREW
Green Building Rough 9/2/2020 Approved DANIEL DREW
Interior/Exterior Lathing 9/11/2020 Approved DANIEL DREW
Insulation 9/18/2020 Approved DANIEL DREW
Drywall Nailing 9/30/2020 Approved DANIEL DREW
Final 12/16/2020 Corrections Issued DANIEL DREW
Green Building Final 12/16/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 12/16/2020 SGSOV Approved DANIEL DREW
Smoke Detectors 12/16/2020 Approved DANIEL DREW
ELECTRICAL-Final 1/22/2021 Approved DANIEL DREW
Final 1/22/2021 OK to Issue CofO DANIEL DREW
HVAC-Final 1/22/2021 Approved DANIEL DREW
PLUMBING-Final 1/22/2021 Approved DANIEL DREW