5331 N TYRONE AVE 91401

Certificate Information: 5331 N TYRONE AVE 91401

Application / Permit
19014-10000-05324
Plan Check / Job No.
B19LA20659
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 400 SF 2ND STORY ADITION TO EXISTING SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/4/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 SERGIO GUTIERREZ
Green Plans Picked Up 10/10/2019 APPLICANT
Corrections Issued 10/24/2019 SERGIO GUTIERREZ
Quality Review Completed 11/6/2019 KESETE HAREGOT
Building Plans Picked Up 11/6/2019 APPLICANT
Plan Check Approved 11/27/2019 SERGIO GUTIERREZ
Issued 12/4/2019 LADBS
CofO in Progress 7/1/2020 MISAEL ESPARZA
Permit Finaled 7/25/2020 MICHAEL SMITH
CofO Issued 7/25/2020 MICHAEL SMITH
Permit Finaled 7/25/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/12/2019 THOMAS LANG
Green Code Cleared 11/12/2019 SERGIO GUTIERREZ
Roof/Waste drainage to street Cleared 11/12/2019 THOMAS LANG
Sewer availability Cleared 11/12/2019 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Hazrati,, Kayvan Naghib; Lic. No.: C60556 465 PUERTO DEL MAR      PACIFIC PALISADES, CA 90272

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 12/18/2019 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 1/16/2020 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 2/25/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 2/25/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 2/25/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 2/25/2020 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 2/25/2020 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 2/28/2020 Approved MISAEL ESPARZA
Deputy Wood Construction 3/3/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/23/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/23/2020 Approved MISAEL ESPARZA
Green Building Rough 3/23/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 3/23/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/23/2020 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Partial Approval MISAEL ESPARZA
Green Building Rough 4/21/2020 Approved TROY SANDERS
Insulation 5/5/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/6/2020 Partial Approval MISAEL ESPARZA
Drywall Nailing 5/15/2020 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 5/15/2020 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 5/15/2020 Approved MISAEL ESPARZA
Drywall Nailing 5/19/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/22/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/22/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/22/2020 Corrections Issued MISAEL ESPARZA
Final 6/22/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 6/22/2020 Approved MISAEL ESPARZA
Green Building Final 6/22/2020 Approved MATTHEW NELSON
HVAC-Final 6/22/2020 Approved MATTHEW NELSON
PLUMBING-Final 6/22/2020 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 6/22/2020 Corrections Issued MISAEL ESPARZA
Pre-Inspection 6/24/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 6/26/2020 Approved MISAEL ESPARZA
Final 6/26/2020 OK to Issue CofO MISAEL ESPARZA
PLUMBING-Final 6/26/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/26/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 6/26/2020 Approved MISAEL ESPARZA