7823 N BELLINGHAM AVE 91605

Certificate Information: 7823 N BELLINGHAM AVE 91605

Application / Permit
19014-10000-05297
Plan Check / Job No.
B19LA20582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; ALL WORK PER WFPP ***"COMPLY WITH DEPARTMENT ORDER effective date 08/16/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/4/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 9/27/2019 SINA KHOSRAVI
Corrections Issued 9/27/2019 SINA KHOSRAVI
Plan Check Approved 12/2/2019 KEVIN MORALES
Issued 12/4/2019 LADBS
CofO in Progress 11/13/2020 LINN MELVIN
Permit Finaled 12/1/2020 ROBERT GOLD
CofO Issued 12/1/2020 ROBERT GOLD
Permit Finaled 12/1/2020 ROBERT GOLD

Permit Application Clearance Information

Construction near power lines Cleared 11/14/2019 RIDWAN HARDY
Address approval Cleared 11/19/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 11/19/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/21/2019 ADRIAN CASTRO
Sewer availability Cleared 11/21/2019 ADRIAN CASTRO

Contact Information

Contractor Green Tech Remodeling & Design Inc; Lic. No.: 1055131-B 5920 WHITSETT AVENUE #3      VALLEY VILLAGE, CA 91607

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2020 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 4/7/2020 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 6/12/2020 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 6/17/2020 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 6/18/2020 Approved RICHARD DOCKUS
HVAC-Rough 7/23/2020 Approved RICHARD DOCKUS
PLUMBING-Rough 7/23/2020 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 7/28/2020 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 7/28/2020 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 8/5/2020 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/7/2020 Partial Approval RICHARD DOCKUS
Insulation 8/12/2020 Approved RICHARD DOCKUS
Drywall Nailing 8/18/2020 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/18/2020 Approved RICHARD DOCKUS
Final 10/29/2020 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/29/2020 SGSOV Not Ready RICHARD DOCKUS
Smoke Detectors 10/29/2020 Approved RICHARD DOCKUS
Final 11/6/2020 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Not Ready RICHARD DOCKUS
Final 11/12/2020 OK to Issue CofO LINN MELVIN
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved LINN MELVIN