2733 W ANGUS ST 90039
Certificate Information: 2733 W ANGUS ST 90039
- Application / Permit
- 19014-10000-05257
- Plan Check / Job No.
- B19LA20380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) TWO STORY SFD WITH ATTACHED GARAGE TO TWO STORY SFD AND ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AND ATTACHED DECK AT THE REAR.. "COMPLY WITH DEPARTMENT ORDER effective date 09/06/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 5/6/2020
- Issuing Office
- Current Status
- CofO Issued on 2/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 11/6/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 11/20/2019 | KESETE HAREGOT |
| Green Plans Picked Up | 12/2/2019 | APPLICANT |
| Applicant returned to address corrections | 12/20/2019 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 3/9/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 4/13/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 4/14/2020 | CHUNG-WEN CHUANG |
| Issued | 5/6/2020 | APPLICANT |
| Building Plans Picked Up | 9/4/2020 | APPLICANT |
| CofO in Progress | 4/19/2024 | JOEL ORDAZ |
| Permit Finaled | 2/25/2025 | DANIEL SANCHEZ |
| CofO Issued | 2/25/2025 | DANIEL SANCHEZ |
| Permit Finaled | 2/25/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JEANETTE VONG |
| Green Code | Cleared | 2/14/2020 | COLIN LOREDO |
| Low Impact Development | Cleared | 2/14/2020 | MITESH PATEL |
| Sewer availability | Cleared | 2/14/2020 | JEANETTE VONG |
| Address approval | Cleared | 2/21/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | CELINA MORENO |
| GPI Written Notices | Cleared | 3/9/2020 | CHUNG-WEN CHUANG |
| Grading Pre-Inspection | Cleared | 3/9/2020 | CHUNG-WEN CHUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hazrati,, Kayvan Naghib; Lic. No.: C60556 | 465 PUERTO DEL MAR PACIFIC PALISADES, CA 90272 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/4/2020 | Corrections Issued | JOHN TCHANG |
| Footing/Foundation/Slab | 12/4/2020 | Not Ready for Inspection | JOHN TCHANG |
| Excavation/Setback/Form/Re-Bar | 12/14/2020 | Approved | JOHN TCHANG |
| Footing/Foundation/Slab | 12/14/2020 | Approved | JOHN TCHANG |
| Green Building Rough | 2/8/2021 | Not Ready for Inspection | JOHN TCHANG |
| Pre-Inspection | 2/8/2021 | Approved | JOHN TCHANG |
| Insulation | 4/8/2021 | Not Ready for Inspection | JOHN TCHANG |
| PLUMBING-Rough | 10/13/2021 | Partial Approval | JOHN TCHANG |
| Shower Pan | 10/13/2021 | Approved | JOHN TCHANG |
| PLUMBING-Rough | 10/26/2021 | Approved | JOHN TCHANG |
| Drywall Nailing | 12/1/2021 | Partial Approval | JOHN TCHANG |
| Green Building Rough | 12/1/2021 | Approved | JOHN TCHANG |
| HVAC-Rough | 12/1/2021 | Corrections Issued | JOHN TCHANG |
| Interior/Exterior Lathing | 12/1/2021 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 6/9/2023 | Corrections Issued | JOEL ORDAZ |
| Drywall Nailing | 6/9/2023 | Not Ready for Inspection | JOEL ORDAZ |
| Final | 6/9/2023 | Corrections Issued | JOEL ORDAZ |
| Green Building Final | 6/9/2023 | Not Ready for Inspection | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | JOEL ORDAZ |
| Smoke Detectors | 6/9/2023 | Corrections Issued | JOEL ORDAZ |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | JOEL ORDAZ |
| Drywall Nailing | 6/14/2023 | Approved | JOEL ORDAZ |
| Final | 6/14/2023 | Corrections Issued | JOEL ORDAZ |
| Green Building Final | 6/14/2023 | Approved | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | JOEL ORDAZ |
| Smoke Detectors | 6/14/2023 | Not Ready for Inspection | JOEL ORDAZ |
| Final | 8/9/2023 | Partial Approval | JOEL ORDAZ |
| Smoke Detectors | 8/9/2023 | Approved | JOEL ORDAZ |
| Final | 12/7/2023 | Not Ready for Inspection | JOEL ORDAZ |
| Insulation | 12/7/2023 | Corrections Issued | JOEL ORDAZ |
| ELECTRICAL-Final | 2/21/2024 | Corrections Issued | JOEL ORDAZ |
| Special/Order Compliance | 3/4/2024 | Approved | JOEL ORDAZ |
| Final | 4/18/2024 | OK to Issue CofO | JOEL ORDAZ |