414 E CAMPDELL ST 90293
Certificate Information: 414 E CAMPDELL ST 90293
- Application / Permit
- 19014-10000-05215
- Plan Check / Job No.
- B19LA20207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO 1 STORY SFD. FULLY SPRINKLERED PER NFPA 13D.
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | JESSE VIDUYA |
| Corrections Issued | 10/10/2019 | JESSE VIDUYA |
| Quality Review Completed | 10/30/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 10/31/2019 | APPLICANT |
| Green Plans Picked Up | 6/30/2020 | APPLICANT |
| Applicant returned to address corrections | 9/23/2020 | JESSE VIDUYA |
| Plan Check Approved | 6/30/2022 | JESSE VIDUYA |
| Issued | 7/18/2022 | APPLICANT |
| CofO Issued | 2/6/2025 | CLAUDIO MORENO |
| Permit Finaled | 2/6/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Green Code | Cleared | 1/16/2020 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 1/31/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 1/31/2020 | MITESH PATEL |
| GPI Written Notices | Cleared | 9/28/2020 | JESSE VIDUYA |
| Grading Pre-Inspection | Cleared | 9/28/2020 | JESSE VIDUYA |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 10/1/2020 | DENNIS BRAGIN |
| Specific Plan | Cleared | 11/16/2020 | PEDRO AYALA |
| Coastal Zone | Cleared | 6/23/2022 | DALIA MOKAYED |
| Miscellaneous | Cleared | 6/23/2022 | DALIA MOKAYED |
| ZI | Cleared | 6/23/2022 | DALIA MOKAYED |
Contact Information
| Contractor | Grace Construction Group Inc; Lic. No.: 1034192-B | 1684 ROOSEVELT AVE LOS ANGELES, CA 90006 |
| Engineer | Wong,, Jim Chu Man; Lic. No.: C69393 | PO BOX 373 GLENDORA, CA 91740 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/12/2022 | Partial Approval | RYAN BARNES |
| Deputy Drilled-In Anchors | 10/7/2022 | Conditional Approval | JOHN MATTILLO |
| Footing/Foundation/Slab | 10/24/2022 | Partial Approval | RYAN BARNES |
| METHANE-Barrier | 10/24/2022 | Not Ready for Inspection | RYAN BARNES |
| METHANE-Subgrade | 10/24/2022 | Not Ready for Inspection | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Not Ready for Inspection | RYAN BARNES |
| Pre-Inspection | 10/25/2022 | Not Ready for Inspection | RYAN BARNES |
| Pre-Inspection | 10/26/2022 | Partial Approval | RYAN BARNES |
| Footing/Foundation/Slab | 12/12/2022 | No Access for Inspection | RYAN BARNES |
| METHANE-Barrier | 12/12/2022 | No Access for Inspection | RYAN BARNES |
| METHANE-Subgrade | 12/12/2022 | No Access for Inspection | RYAN BARNES |
| Pre-Inspection | 12/12/2022 | No Access for Inspection | RYAN BARNES |
| Pre-Inspection | 12/20/2022 | Not Ready for Inspection | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Not Ready for Inspection | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 3/14/2023 | Approved | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | No Access for Inspection | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Partial Approval | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Partial Approval | RYAN BARNES |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 9/27/2023 | Approved | RYAN BARNES |
| Green Building Rough | 9/27/2023 | Approved | RYAN BARNES |
| HVAC-Rough | 9/27/2023 | Approved | RYAN BARNES |
| METHANE-Rough | 9/27/2023 | Approved | RYAN BARNES |
| PLUMBING-Rough | 9/27/2023 | Approved | RYAN BARNES |
| Insulation | 10/11/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 10/11/2023 | Approved | RYAN BARNES |
| Drywall Nailing | 10/25/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 1/12/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 1/12/2024 | Corrections Issued | ANDREW BEELI |
| Shower Pan | 1/12/2024 | Approved | ANDREW BEELI |
| Gas Test | 1/17/2024 | Approved | RYAN BARNES |
| PLUMBING-Rough | 1/17/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 6/10/2024 | Partial Approval | RYAN BARNES |
| ELECTRICAL-Final | 7/8/2024 | Partial Approval | JOHN MATTILLO |
| Service/Power Release | 7/8/2024 | Approved | JOHN MATTILLO |
| ELECTRICAL-Final | 9/11/2024 | Corrections Issued | RYAN BARNES |
| HVAC-Final | 9/11/2024 | Approved | RYAN BARNES |
| PLUMBING-Final | 9/11/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 9/27/2024 | Approved | RYAN BARNES |
| Final | 9/27/2024 | Conditional Approval | RYAN BARNES |
| Footing/Foundation/Slab | 9/27/2024 | Approved | RYAN BARNES |
| Green Building Final | 9/27/2024 | Approved | RYAN BARNES |
| METHANE-Barrier | 9/27/2024 | Approved | RYAN BARNES |
| METHANE-Subgrade | 9/27/2024 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 9/27/2024 | Approved | RYAN BARNES |