2509 S HILLCREST DR 90016

Certificate Information: 2509 S HILLCREST DR 90016

Application / Permit
19014-10000-05208
Plan Check / Job No.
B19LA20183
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
First and second story additions to (E) SFD and major remodel entire (E) SFD. (N) attached carport to (E) SFD. Fire sprinkler is equipped throughout the building.
Permit Issued
Issued on 3/11/2021
Issuing Office
Current Status
Issued on 3/11/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 HELEN NGUYEN
Corrections Issued 10/15/2019 HELEN NGUYEN
Quality Review Completed 10/27/2019 YOUNG KIM
Applicant returned to address corrections 6/9/2020 HELEN NGUYEN
Applicant returned to address corrections 7/13/2020 HELEN NGUYEN
Applicant returned to address corrections 7/15/2020 HELEN NGUYEN
Applicant returned to address corrections 8/14/2020 HELEN NGUYEN
Applicant returned to address corrections 8/17/2020 HELEN NGUYEN
Building Plans Picked Up 8/17/2020 APPLICANT
Green Plans Picked Up 8/17/2020 APPLICANT
Plan Check Approved 2/25/2021 HELEN NGUYEN
Issued 3/11/2021 APPLICANT

Permit Application Clearance Information

Green Code Cleared 8/12/2020 HELEN NGUYEN
Sewer availability Cleared 9/25/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 9/28/2020 JUAN ASHTON
Low Impact Development Cleared 1/20/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/26/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/6/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 4/16/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval STUART CHAPMAN
Green Building Rough 5/26/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 5/26/2021 Partial Approval STUART CHAPMAN
MERV13>=Rough 5/26/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/26/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/13/2021 Partial Approval DAVID FEILER
Green Building Rough 7/13/2021 Not Ready for Inspection DAVID FEILER
MERV13>=Rough 7/13/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 12/16/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2021 Partial Approval STUART CHAPMAN
Green Building Rough 12/16/2021 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 12/16/2021 Approved STUART CHAPMAN
Deputy Wood Construction 1/26/2022 Approved STUART CHAPMAN
Green Building Rough 2/4/2022 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 2/4/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 3/7/2022 Approved KATHRYN BUTTERWORTH
HVAC-Rough 3/7/2022 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 3/7/2022 Corrections Issued KATHRYN BUTTERWORTH
Shower Pan 3/7/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 3/7/2022 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/15/2022 Approved STUART CHAPMAN
HVAC-Rough 3/15/2022 Approved STUART CHAPMAN
PLUMBING-Rough 3/15/2022 Approved STUART CHAPMAN
Insulation 3/29/2022 Approved STUART CHAPMAN
Shower Pan 3/29/2022 Approved STUART CHAPMAN
Drywall Nailing 4/7/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 4/7/2022 Approved STUART CHAPMAN
Drywall Nailing 4/15/2022 Approved STUART CHAPMAN
Underground Mechanical 5/19/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/6/2022 Partial Approval STUART CHAPMAN
Shower Pan 6/6/2022 Approved STUART CHAPMAN
Service/Power Release 6/29/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 8/11/2022 Approved STUART CHAPMAN
Gas Test 10/3/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 10/18/2022 Not Ready for Inspection STUART CHAPMAN
Final 10/18/2022 Corrections Issued STUART CHAPMAN
Gas Test 10/18/2022 Approved STUART CHAPMAN
HVAC-Final 10/18/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 10/18/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 7/5/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Final 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
MERV13>=Final 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Final 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY