1563 S GENESEE AVE 90019

Certificate Information: 1563 S GENESEE AVE 90019

Application / Permit
19014-10000-05185
Plan Check / Job No.
B19LA20030
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING OF (E) GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 & SB 229 AND ADDITION.
Permit Issued
Issued on 3/10/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 EVERARDO SANTOS
Corrections Issued 10/15/2019 EVERARDO SANTOS
Green Plans Picked Up 10/22/2019 APPLICANT
Quality Review Completed 10/30/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/6/2019 APPLICANT
Plan Check Approved 12/3/2019 EVERARDO SANTOS
Issued 3/10/2020 LADBS
CofO in Progress 2/3/2021 STUART CHAPMAN
Permit Finaled 4/15/2021 DEROLD HAUFF
CofO Issued 4/15/2021 DEROLD HAUFF
Permit Finaled 4/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/6/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/6/2019 THOMAS LANG
Sewer availability Cleared 11/6/2019 THOMAS LANG
Green Code Cleared 11/27/2019 VIVIAN LAO
Low Impact Development Cleared 11/27/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 11/27/2019 THOMAS LANG

Contact Information

Architect Phakos,, Cynthia; Lic. No.: C23352 9010 RANGELY AVE      WEST HOLLYWOOD, CA 90048
Contractor Furer Construction Inc; Lic. No.: 988604-B 3133 ROBERTS AVE      CULVER CITY, CA 90232
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/22/2020 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 4/23/2020 Partial Approval DAVID CHAN
METHANE-Subgrade 4/23/2020 Partial Approval DAVID CHAN
Masonry Wall/Backfill 5/5/2020 Partial Approval DAVID CHAN
METHANE-Rough 7/2/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 7/2/2020 Partial Approval DAVID CHAN
METHANE-Subgrade 7/7/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 7/8/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 7/23/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 7/30/2020 Partial Approval DAVID CHAN
METHANE-Barrier 7/30/2020 Approved DAVID CHAN
METHANE-Subgrade 7/30/2020 Approved DAVID CHAN
HVAC-Rough 8/14/2020 Not Ready for Inspection DAVID CHAN
METHANE-Final 8/14/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 8/14/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 8/24/2020 Partial Inspection DAVID CHAN
ELECTRICAL-Rough 8/24/2020 Approved DAVID CHAN
Green Building Rough 8/24/2020 Approved DAVID CHAN
HVAC-Rough 8/24/2020 Approved DAVID CHAN
METHANE-Rough 8/24/2020 Approved DAVID CHAN
Shower Pan 8/24/2020 Approved DAVID CHAN
Gas Test 8/27/2020 Not Ready for Inspection SABAS ALONSO
Insulation 8/27/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/27/2020 Partial Approval SABAS ALONSO
Drywall Nailing 9/1/2020 Approved DAVID CHAN
Interior/Exterior Lathing 9/1/2020 Approved DAVID CHAN
ELECTRICAL-Final 10/1/2020 Not Ready for Inspection STUART CHAPMAN
Final 10/1/2020 Corrections Issued STUART CHAPMAN
Gas Test 10/1/2020 Approved STUART CHAPMAN
HVAC-Final 10/1/2020 Approved STUART CHAPMAN
PLUMBING-Final 10/1/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/22/2020 Approved DAVID CHAN
ELECTRICAL-Final 10/22/2020 Approved DAVID CHAN
Final 10/22/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 10/22/2020 Approved DAVID CHAN
Green Building Final 10/22/2020 Approved DAVID CHAN
METHANE-Final 10/22/2020 Approved DAVID CHAN
METHANE-Rough 10/22/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Not Ready DAVID CHAN
Service/Power Release 10/22/2020 Not Required DAVID CHAN
Smoke Detectors 10/22/2020 Approved DAVID CHAN
Final 11/12/2020 Corrections Issued DAVID CHAN
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved DAVID CHAN
Service/Power Release 11/12/2020 Approved DAVID CHAN
Final 2/2/2021 OK to Issue CofO STUART CHAPMAN