1563 S GENESEE AVE 90019
Certificate Information: 1563 S GENESEE AVE 90019
- Application / Permit
- 19014-10000-05184
- Plan Check / Job No.
- B19LA20030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SINGLE FAMILY DWELLING AND APPROXIMATE 700 SF REMODEL.
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | EVERARDO SANTOS |
| Corrections Issued | 10/15/2019 | EVERARDO SANTOS |
| Green Plans Picked Up | 10/22/2019 | APPLICANT |
| Quality Review Completed | 10/30/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Plan Check Approved | 12/3/2019 | EVERARDO SANTOS |
| Issued | 3/10/2020 | LADBS |
| CofO in Progress | 2/3/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
| CofO Issued | 2/6/2021 | DEROLD HAUFF |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/6/2019 | THOMAS LANG |
| Green Code | Cleared | 11/27/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 11/27/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/27/2019 | THOMAS LANG |
Contact Information
| Architect | Phakos,, Cynthia; Lic. No.: C23352 | 9010 RANGELY AVE WEST HOLLYWOOD, CA 90048 |
| Contractor | Furer Construction Inc; Lic. No.: 988604-B | 3133 ROBERTS AVE CULVER CITY, CA 90232 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/22/2020 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/23/2020 | Partial Approval | DAVID CHAN |
| METHANE-Barrier | 4/23/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 4/23/2020 | Approved | DAVID CHAN |
| Masonry Wall/Backfill | 5/5/2020 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/14/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 6/9/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 6/15/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 6/15/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 6/19/2020 | Conditional Approval | DAVID CHAN |
| Green Building Rough | 6/19/2020 | Approved | DAVID CHAN |
| METHANE-Rough | 6/19/2020 | Approved | DAVID CHAN |
| Insulation | 6/26/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/7/2020 | Conditional Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 7/27/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 7/27/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 8/3/2020 | Approved | MATTHEW NUCKOLLS |
| Gas Test | 8/3/2020 | Approved | MATTHEW NUCKOLLS |
| ELECTRICAL-Final | 9/21/2020 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Final | 9/21/2020 | Partial Inspection | RUBEN SALAS |
| Service/Power Release | 9/21/2020 | Partial Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 9/22/2020 | Approved | DAVID CHAN |
| Final | 9/22/2020 | No Access for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 9/22/2020 | Approved | DAVID CHAN |
| HVAC-Final | 9/22/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Not Ready | DAVID CHAN |
| Smoke Detectors | 9/22/2020 | No Access for Inspection | DAVID CHAN |
| Final | 9/24/2020 | Not Ready for Inspection | DAVID CHAN |
| HVAC-Final | 9/24/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 9/24/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 9/25/2020 | Approved | DAVID CHAN |
| Service/Power Release | 9/25/2020 | Not Ready for Inspection | DAVID CHAN |
| Final | 10/22/2020 | Not Ready for Inspection | DAVID CHAN |
| Green Building Final | 10/22/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Approved | DAVID CHAN |
| Service/Power Release | 10/22/2020 | Approved | DAVID CHAN |
| Smoke Detectors | 10/22/2020 | Approved | DAVID CHAN |
| Final | 11/12/2020 | Corrections Issued | DAVID CHAN |
| Final | 2/2/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |