2003 N EL CERRITO PL 90068
Certificate Information: 2003 N EL CERRITO PL 90068
- Application / Permit
- 19014-10000-05148
- Plan Check / Job No.
- B19LA19870
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 598.7 SF ADDITION, INTERIOR REMODEL. NEW DECK AND 2 PARKING SPACES.
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Metro
- Current Status
- Issued on 4/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | SALVADOR QUINTANILLA |
| Corrections Issued | 9/30/2019 | SALVADOR QUINTANILLA |
| Quality Review Completed | 10/1/2019 | PETER KIM |
| Building Plans Picked Up | 10/25/2019 | APPLICANT |
| Green Plans Picked Up | 10/25/2019 | APPLICANT |
| Applicant returned to address corrections | 11/21/2019 | SALVADOR QUINTANILLA |
| Plan Check Approved | 11/27/2019 | SALVADOR QUINTANILLA |
| Issued | 4/22/2021 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/28/2019 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/28/2019 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/28/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2019 | ERIK BEASLEY |
| Highway dedication | Cleared | 10/28/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/28/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 10/30/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/30/2019 | THOMAS LANG |
| Green Code | Cleared | 11/7/2019 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 11/21/2019 | SALVADOR QUINTANILLA |
| Hydrant and Access approval | Cleared | 11/27/2019 | JEREMY CARTER |
Contact Information
| Architect | Eyster,, Jeffrey Jon; Lic. No.: C35218 | 7288 SUNSET BLVD #201 LOS ANGELES, CA 90046 |
| Contractor | Custom Interiors Design Fixtures Corp; Lic. No.: 910980-B | 7647 INDUSTRY AVENUE #200 PICO RIVERA, CA 90660 |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/9/2021 | Approved | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 9/14/2021 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Partial Approval | BRIAN SULLIVAN |
| Structural Steel Frame | 9/15/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/20/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Wood Construction | 10/22/2021 | Conditional Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 2/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/18/2022 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 2/18/2022 | Corrections Issued | COREY HUPP |
| Green Building Rough | 2/18/2022 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 2/18/2022 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 2/18/2022 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 2/25/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 2/25/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | BRIAN SULLIVAN |
| Smoke Detectors | 2/25/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 3/3/2022 | Approved | BRIAN SULLIVAN |
| Shower Pan | 3/3/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 3/18/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 6/23/2022 | Approved | BRIAN SULLIVAN |
| Final | 6/23/2022 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 6/23/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 6/23/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 6/23/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 6/23/2022 | Approved | BRIAN SULLIVAN |
| Final | 7/7/2022 | Corrections Issued | BRIAN SULLIVAN |