1839 S COCHRAN AVE 90019

Certificate Information: 1839 S COCHRAN AVE 90019

Application / Permit
19014-10000-05134
Plan Check / Job No.
B19LA19818
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSURE OF A SECOND FLOOR EXTERIOR BALCONY INTO BATHROOM
Permit Issued
Issued on 4/30/2020
Issuing Office
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2019 APPLICANT
Assigned to Plan Check Engineer 9/18/2019 ZAW HAN
Corrections Issued 9/18/2019 ZAW HAN
Plan Check Approved 9/20/2019 PRANITA SHAH
Issued 4/30/2020 APPLICANT
Building Plans Picked Up 4/30/2020 APPLICANT
CofO in Progress 9/11/2020 DAVID CHAN
Permit Finaled 4/24/2021 DEROLD HAUFF
CofO Issued 4/24/2021 DEROLD HAUFF
Permit Finaled 4/24/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/18/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 9/18/2019 ERIK BEASLEY
Sewer availability Cleared 9/18/2019 ERIK BEASLEY
ZA Case Cleared 9/18/2019 RICHARD REASER

Contact Information

Architect Best,, Richard Allen; Lic. No.: C17334 1275 BEVERLY ESTATES DR.      BEVERLY HILLS, CA 90210
Contractor Silverlake Construction; Lic. No.: 908872-B PO BOX 1272      WILMINGTON, CA 90748

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/4/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 5/4/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 5/4/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 5/7/2020 Approved DAVID CHAN
Shower Pan 5/26/2020 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Approved DAVID CHAN
Wood Frame 5/29/2020 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 6/8/2020 Conditional Approval DAVID CHAN
Green Building Rough 6/8/2020 Approved DAVID CHAN
Insulation 6/8/2020 Partial Approval DAVID CHAN
Interior/Exterior Lathing 6/8/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 6/15/2020 Approved DAVID CHAN
ELECTRICAL-Rough 6/15/2020 Approved DAVID CHAN
Insulation 6/15/2020 Approved DAVID CHAN
Drywall Nailing 6/18/2020 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 6/18/2020 Partial Approval THOMAS LOGRASSO
Final 9/10/2020 OK to Issue CofO DAVID CHAN
Green Building Final 9/10/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Approved DAVID CHAN
Smoke Detectors 9/10/2020 Approved DAVID CHAN