24420 S DEEPWATER AVE 90744
Certificate Information: 24420 S DEEPWATER AVE 90744
- Application / Permit
- 19014-10000-05124
- Plan Check / Job No.
- B19LA19766
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE/STORAGE INTO AN ACCESSORY DWELLING UNIT WITH COVERED PATIO ADDITION PER LAMC 12.22A.33.
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 3/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | JOHNNY WU |
| Corrections Issued | 10/8/2019 | JOHNNY WU |
| Quality Review Completed | 10/17/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 10/18/2019 | APPLICANT |
| Green Plans Picked Up | 10/18/2019 | APPLICANT |
| Applicant returned to address corrections | 8/13/2021 | JOHNNY WU |
| Applicant returned to address corrections | 8/17/2021 | JOHNNY WU |
| Plan Check Approved | 8/17/2021 | JOHNNY WU |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 3/2/2023 | EUGENE CASSIDY |
| CofO Issued | 3/9/2023 | ANSON MAGLASANG |
| Permit Finaled | 3/9/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | CELINA MORENO |
| Sewer availability | Cleared | 12/3/2019 | CELINA MORENO |
| Green Code | Cleared | 2/4/2020 | JOHNNY WU |
| ZI | Cleared | 12/15/2020 | SARAHI ORTEGA |
| Abandoned oil well | Cleared | 3/24/2021 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 3/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/2/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/6/2021 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/24/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 10/26/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 10/26/2021 | Approved | JOHN KLARIN |
| Pre-Inspection | 10/26/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 11/29/2021 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 12/6/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 1/27/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 1/27/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/9/2022 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 2/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 4/12/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/4/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 5/4/2022 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 5/4/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/10/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 6/10/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/27/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/27/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/27/2022 | Approved | EUGENE CASSIDY |
| Insulation | 7/5/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/5/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/18/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/27/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 7/28/2022 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 10/20/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | JOHN KLARIN |
| Final | 12/1/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/1/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 12/1/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/1/2022 | Approved | JOHN KLARIN |
| Final | 12/13/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/27/2023 | Approved | EUGENE CASSIDY |
| Final | 2/27/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/27/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/27/2023 | Approved | EUGENE CASSIDY |