345 S SAN PEDRO ST 90013

Certificate Information: 345 S SAN PEDRO ST 90013

Application / Permit
19014-10000-05111
Plan Check / Job No.
B19LA19714
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT FOR OFFICES TO ALL 3 STORIES. NEW PARTITIONS, NEW CEILINGS, AND FINISHES. NEW ACCESSIBLE RESTROOMS. REMOVE INTERIOR STAIRS AND INFILL 1ST AND 2ND FLOOR.
Permit Issued
Issued on 1/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 KEVIN MORALES
Corrections Issued 10/4/2019 KEVIN MORALES
Quality Review Completed 10/12/2019 YOUNG KIM
Green Plans Picked Up 10/15/2019 APPLICANT
Building Plans Picked Up 10/17/2019 APPLICANT
Disabled Access Plans Picked Up 10/25/2019 APPLICANT
Plan Check Approved 12/20/2019 KEVIN MORALES
Issued 1/16/2020 LADBS
CofO in Progress 12/7/2021 TIMOTHY BUXTON
Permit Finaled 12/7/2021 TED RIES
CofO Issued 12/7/2021 TED RIES
Permit Finaled 12/7/2021 TED RIES

Permit Application Clearance Information

Green Code Cleared 11/7/2019 COLIN LOREDO
Project located in CRA area Cleared 12/13/2019 GRACIELA ACOSTA
DAS Clearance Cleared 12/20/2019 KEVIN MORALES
ZA Case Cleared 12/20/2019 SOPHIE GABEL-SCHEINBAU

Contact Information

Architect Mechur,, Ralph Steven; Lic. No.: C11683 3400 AIRPORT AVE 5      SANTA MONICA, CA 90405
Contractor Oakmont Builders Inc; Lic. No.: 978123-B 9671 SUNLAND BLVD 2A      LOS ANGELES, CA 91040

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 2/24/2020 Corrections Issued KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 3/24/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 5/14/2020 Conditional Approval DANIEL COLLINS
Wood Frame 5/14/2020 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 8/3/2020 Partial Approval NICK DANERI
Drywall Nailing 8/17/2020 Approved TIMOTHY BUXTON
T-Bar Ceiling 10/16/2020 Not Ready for Inspection LANNY MERRICK
T-Bar Ceiling 11/9/2020 Approved DANIEL COLLINS
Final 8/31/2021 Not Ready for Inspection TIMOTHY BUXTON
Footing/Foundation/Slab 8/31/2021 Approved TIMOTHY BUXTON
Green Building Final 8/31/2021 Approved TIMOTHY BUXTON
Green Building Rough 8/31/2021 Approved TIMOTHY BUXTON
METHANE-Barrier 8/31/2021 Approved TIMOTHY BUXTON
METHANE-Final 8/31/2021 Approved TIMOTHY BUXTON
METHANE-Rough 8/31/2021 Approved TIMOTHY BUXTON
METHANE-Subgrade 8/31/2021 Approved TIMOTHY BUXTON
Reinforced Masonry Frame 8/31/2021 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 8/31/2021 Approved TIMOTHY BUXTON
Final 9/20/2021 Corrections Issued DARRYL ARNOLD
Final 9/24/2021 Conditional Approval TIMOTHY BUXTON