345 S SAN PEDRO ST 90013
Certificate Information: 345 S SAN PEDRO ST 90013
- Application / Permit
- 19014-10000-05111
- Plan Check / Job No.
- B19LA19714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT FOR OFFICES TO ALL 3 STORIES. NEW PARTITIONS, NEW CEILINGS, AND FINISHES. NEW ACCESSIBLE RESTROOMS. REMOVE INTERIOR STAIRS AND INFILL 1ST AND 2ND FLOOR.
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | KEVIN MORALES |
| Corrections Issued | 10/4/2019 | KEVIN MORALES |
| Quality Review Completed | 10/12/2019 | YOUNG KIM |
| Green Plans Picked Up | 10/15/2019 | APPLICANT |
| Building Plans Picked Up | 10/17/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/25/2019 | APPLICANT |
| Plan Check Approved | 12/20/2019 | KEVIN MORALES |
| Issued | 1/16/2020 | LADBS |
| CofO in Progress | 12/7/2021 | TIMOTHY BUXTON |
| Permit Finaled | 12/7/2021 | TED RIES |
| CofO Issued | 12/7/2021 | TED RIES |
| Permit Finaled | 12/7/2021 | TED RIES |
Permit Application Clearance Information
| Green Code | Cleared | 11/7/2019 | COLIN LOREDO |
| Project located in CRA area | Cleared | 12/13/2019 | GRACIELA ACOSTA |
| DAS Clearance | Cleared | 12/20/2019 | KEVIN MORALES |
| ZA Case | Cleared | 12/20/2019 | SOPHIE GABEL-SCHEINBAU |
Contact Information
| Architect | Mechur,, Ralph Steven; Lic. No.: C11683 | 3400 AIRPORT AVE 5 SANTA MONICA, CA 90405 |
| Contractor | Oakmont Builders Inc; Lic. No.: 978123-B | 9671 SUNLAND BLVD 2A LOS ANGELES, CA 91040 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 2/24/2020 | Corrections Issued | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 3/24/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 5/14/2020 | Conditional Approval | DANIEL COLLINS |
| Wood Frame | 5/14/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 8/3/2020 | Partial Approval | NICK DANERI |
| Drywall Nailing | 8/17/2020 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 10/16/2020 | Not Ready for Inspection | LANNY MERRICK |
| T-Bar Ceiling | 11/9/2020 | Approved | DANIEL COLLINS |
| Final | 8/31/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 8/31/2021 | Approved | TIMOTHY BUXTON |
| Green Building Final | 8/31/2021 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 8/31/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 8/31/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 8/31/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 8/31/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 8/31/2021 | Approved | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 8/31/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 8/31/2021 | Approved | TIMOTHY BUXTON |
| Final | 9/20/2021 | Corrections Issued | DARRYL ARNOLD |
| Final | 9/24/2021 | Conditional Approval | TIMOTHY BUXTON |